Issues when inserting P6 Programme
- Created
- 2
- 3
Hello house,
I will appreciate any help on the issue I am currently facing:
I copied a subcontractor Xer File to my Master Schedule . This plan was moved to a WBS within the master schedule, however I am now facing an issue where a number of activities adopted a global calendar therefore their dates are all over the place
Is there a way I could this or I'll need to go back to the inserted programme and change the calendar manually ?
Secondly, when I aligned the calendar and schedule the programme, I notice the inserted programme now in a WBS of the master schedule is generating a negative float despite maintaning the same DD to the last secs.
Any guidance on the above 2 issues will be highly appreciated
2 replies
Oldest firstLog in or join to reply