Issues when inserting P6 Programme

Eliuh AkinpeloyeMember for 8 years 2 months
Created
2
3
0

Hello house,

I will appreciate any help on the issue I am currently facing:

I copied a subcontractor Xer File to my Master Schedule . This plan was moved to a WBS within the master schedule, however I am now facing an issue where  a number of activities adopted a global calendar therefore their dates are all over the place

 

Is there a way I could this or I'll need to go back to the inserted programme and change the calendar manually ?

Secondly, when I aligned the calendar and schedule the programme, I notice the inserted programme now in a WBS of the master schedule is generating a negative float despite maintaning the same DD to the last secs.

Any guidance on the above 2 issues will be highly appreciated

 

2 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    3 optionsoption #1you can

    3 options

    option #1

    you can choose to not import calendars during the import process

    Option #2

    add column for calendars and do the 1st activity and the do a fill down

    Option #3

    run a global change to make all of the calendars the same 

  2. 0
    Zoltan Palffy ·

    3 optionsoption #1you can

    3 options

    option #1

    you can choose to not import calendars during the import process

    Option #2

    add column for calendars and do the 1st activity and the do a fill down

    Option #3

    run a global change to make all of the calendars the same 

Log in or join to reply