Hi everyone, 

Has anyone ever written formula for " DCMA 14"? 

 

If yes, can you share it please.

2 replies

Oldest first
  1. 0
    Peter Holroyd ·

    There's loads of P6 add ons

    There's loads of P6 add ons that have this covered.

  2. 0
    Zoltan Palffy ·

    also in version 22.4 there is

    also in version 22.4 there is a tool in P6 its under view then check schedule its a list like the DCMA 14 point   

    also look for a utility called xer reader it uses an xer file and performs the 14 point for you