In P6, how to show a milestone's date to reflect the earliest start date of the group predecessors' activities rather than total

Kannan BalaramMember for 10 years 8 months
Created
2
4
0

Dear All,

In P6, how to show a milestone's date to reflect the earliest start date of the group predecessors' activities rather than total float driving from the group predecessors' activities.

 

In the above snapshot, for my reporting purpose, I expect the start date for Activity ID300 from the group of predecessors should reflect the earliest start date of 01-08-2023 instead of total float driven predecessor's activity's start date of 29-08-2023

BR, Kannan

2 replies

Oldest first
  1. 0
    Rodney Jones ·

    Hello Kannan Balaram,I think

    Hello Kannan Balaram,

    I think your screenshot is missing. So you want to see the Milestone Start Date without all the Total Float?

    What about creating an Activity UDF called 'WTF' (Without Total Float), UDF Type will be Date, then you can run a global change calculation of:

    WTF = Start Date minus Total Float.

     

    I haven't tested the concept but it is a start and other minds better informed can help.

     

    Rod

  2. 0
    Paul Harris ·

    You need to make the

    You need to make the Milestone Task a LOE and hook up to all the predecessor tasks with both a FS and a FF, then format the LOE Tasks to show only a Milestone.

    If you want to show other LOE tasks as a LOE then you will need to create a Activity Code for normal and milestone LOE tasks and a bar style for both and apply the filter to the two LOE bar styles in the Bars form.

    Regards

    Paul E Harris

    www.eh.com.au

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?