Primavera Import: exported 1 line for the format, but copy and paste of "format" to the dates below does not work.

John ReevesMember for 13 years 5 months
Created
2
3
0

Primavera Import: exported 1 line for the format, but copy and paste of "format" to the dates below does not work.  It will not produce the black triangle in the upper left like the real exported dates  which states "Text Date with digit year" and when I copy the date format it turns the dates into excel dates in number format.  2nd question, does putting a ' mark in front of the id - is that enough to make it importable.  I have imported on and off for years - I just forget the nuances.

2 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    you cant import start and

    you cant import start and finish dates those are claulated

    you can import constraint dates 

    you  can import actual dates

    1st export 1 activity of what you want thne use that as a template to import it back into p6

  2. 0
    Zoltan Palffy ·

    you cant import start and

    you cant import start and finish dates those are claulated

    you can import constraint dates 

    you  can import actual dates

    1st export 1 activity of what you want thne use that as a template to import it back into p6