Primavera 8.2 - Negative Float Issue

Chris FeaganMember for 12 years 11 months
Created
0
4
0

Our team has run into an issue with negative float being calculated to a Level of Effort task.  Background: We work in a very large Integrated Master Schedule (IMS) that encompasses in excess of 30 individual projects.  These projects have multiple tasks that are logically linked from one project to another.

 

The current issue: I have a LOE that only has a SS relationship to a task within that project (with 0 Days Total Float) and a FF relationship to another task within that project (with 232 Days Total Float).  The problem is that the LOE indicates -620 Days Total Float.  There are no constraints (Start On or After, Finish On or After, etc.) assigned.  I must be missing something?

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?