Hi All
I am looking for a way of defining a Custom Report that shows Summary Tasks together with Resources attached to the sub tasks.
Does anyone know if this is possible and if so how do I achieve it.
Look forward to hearing fom you.
Kind regards
Tony

1 reply

Oldest first
  1. 0
    Paul Harris ·
    Tools,Project Utilitiss, Summarize might do it for you.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
    www.eh.com.au