SKYSCRAPER - SAMPLE CPM SCHEDULE
In the Open Standard
NC
N Curgus PSPMember for 23 years 3 months
- Created
- 27
- 14
0
27 replies
Oldest first- 0COCharleston-Joseph Orbe ·Dear All,
I’m surprise with the response. Very few are involve in building works, most are involve with other trade. What does this "sample Skycraper CPM means, maybe someday there will be migration to building works.
In my reply no 2
How high is your SKYCRAPER???? nobody answer
You want the sample of the Highest Building in Planet Earth. no answer
Also provide a typical floor area. no answer
"Maybe we can come up with something." This is very important.
What really I have in mind is a collaoboration of the best of the best plannning planet can offer. We, not me alone, will prepare a CPM Schedule using hypothetical tallest tower/skycrapper in the Universe.
How to do this?????
It will be unfold if our work will give us free time.
Cheers,
Sensei
- 0RRRonald Romero ·fellow PPers,
I believe that even though i did most of my planning was up to three floors , planning for a skycraper from first floor up will almost be the same save for some variation in the design and use of the floor it will be typically a copy of the floor preceeding it .
Am I right? So Charles send me a sample at ronnieksa@yahoo.com to learn some words, verbs and terminology planners are using when planning a skycrapper from ground up.
Regards,
- 0COCharleston-Joseph Orbe ·Ronald,
The one I’m thinking of generating start design phase (concept, schematic, design development, contract documentation) Tender Phase, Construction Phase and Post Construction (defect liability period).
The Skycraper I have in mind is the tallest in the Universe 1500 storey high above ground level (4,500 meters), compose of three towers (skycraper) within built up area (podium and retails).
- 0AMArmando Moriles ·Sensei,
I really appreciate your idea and I would like to share any idea...
To start with...
1. If our building is 1,500 storeys excluding basements and podium and assuming a fast 5 day per floor structural works cycle using 5 complete form sets, etc...that would take us 7,500 calendar days;
2. At 4,500 m high (14,760 feet) would be beyond air traffic height limitation. We may require sovereignty of our air space;
3. I suggest we need a high altitude helicopter to do that;
4. etc...
Arman - 0COChris Oggham ·Hi Arman,
I found your post #22 extremely interesting, pointing out as it did the implausibility and impracticality of Charlie’s skyscraper. I’m sure it won’t be too long before Charlie responds with a detailed explanation of how to resolve all of the difficulties.
I’m sure he’ll also get round to supplying the schedule that he promised to so many people as well, however, I won’t be holding my breath.
Chris Oggham - 0AMAkhtar Mehdi ·
hiiiii Could you pls send me
hiiiii
Could you pls send me the schedule for the high rise building at
Note : I am attending PMI -SP classes these days and learnt about this most usefull site during classes.
- 0ZPZoltan Palffy ·
dig foundationspour
dig foundations
pour foundations
set steel in basement
set steel in lobby
set steel 2nd floor and repeate for as many floor that you have
set roof steel
set exterior skin and windows and repeate for as many floor that you have
fit out basement
fit out lobby
fit out 2nd floor and repeate for as many floor that you have
done
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?