SKYSCRAPER - SAMPLE CPM SCHEDULE

N Curgus PSPMember for 23 years 3 months
Created
27
14
0

DOES ANYONE HAVE A CONSTRUCTION SCHEDULE FOR A SKYSCRAPER THAT CAN BE SHARED? ALSO ANY ARTICLES/TIPS WILL BE APPRECIATED.

THANKS

NC

27 replies

Oldest first
  1. 0
    Charleston-Joseph Orbe ·
    Hi,

    How high is your SKYCRAPER????

    You want the sample of the Highest Building in Planet Earth.

    Also provide a typical floor area.

    Maybe we can come up with something.

    Cheers,
  2. 0
    Kier Legard ·

    Hi Charles,

    Could you please send me any sample projects in High rise building.My mail Kier_70@yahoo.com


    Regards,

    kier
  3. 0
    Kamal Khemchandani ·
    Hi Charles,
    While you are handing out the wbs for the highest building on Planet earth some guy in the middle east is making one double the height...so lets see how upto date the WBS really is..do send me one at kamalkhemu@hotmail.com

    Best regards..
  4. 0
    A D ·
    Hi Charles,

    By any chance, do you have any logistics plan for the high-rise buildings. I have asked it before on PP, but no help. What I am using now is totally unpresentable. If you have any, plz share. Can send the mail on ravirajab@yahoo.co.in
  5. 0
    Gordon Blair ·
    Charlie’s still hawking round that WBS they used on the tower of Babel ;o)
  6. 0
    Nar Thap ·
    Hi Charls, drop a copy to me as well at narnor2002@yahoo.com
    your help will be appreciated.
    regards,
  7. 0
    Sam Mohan ·
    Hi Charles,


    could you please drop me copy as well , samohan4@hotmail.com

    thanks

    sam
  8. 0
    Mohamed Edris ·
    Hi Charles,

    Would you pls send me a copy as well?

    Email: edrismido@hotmail.com


    Thnx
    Mohd
  9. 0
    Gencay Yedikardesler ·

    Hi Charles,

    Would you pls send me a copy too?
    Email: gencayy@yahoo.com

    Thnks
    Gencay
  10. 0
    Sridhar J ·


    Hi Charls

    Could you pls send me a copy too at my mail adress -jxsridhar@yahoo.com


    Regards
    Sridhar
  11. 0
    Charan Hari ·
    Hi Charles,

    Would you pls send me a copy too?
    Email: charanrao@hotmail.com

    Your help would be appreciated.

    Cheers,
    Cherry
  12. 0
    Kier Legard ·
    Hi Charles ,


    Havent receiced your skycraper program.




    Cheers
    kier
  13. 0
    Charleston-Joseph Orbe ·
    Dear All,

    I’m surprise with the response. Very few are involve in building works, most are involve with other trade. What does this "sample Skycraper CPM means, maybe someday there will be migration to building works.

    In my reply no 2
    How high is your SKYCRAPER???? nobody answer
    You want the sample of the Highest Building in Planet Earth. no answer
    Also provide a typical floor area. no answer

    "Maybe we can come up with something." This is very important.

    What really I have in mind is a collaoboration of the best of the best plannning planet can offer. We, not me alone, will prepare a CPM Schedule using hypothetical tallest tower/skycrapper in the Universe.

    How to do this?????

    It will be unfold if our work will give us free time.

    Cheers,
    Sensei




  14. 0
    Zeinab El-Beialy ·
    HI,

    Would you please send me the SKYCRAPER programme and activities on my e-mail: zeinab100@gmail.com
    thanks.
  15. 0
    Kier Legard ·


    Hi Sensei Charles,




    Are you involve in the construction of the highest building now? Can u please share to us your construction programme?


    Regards,
    kier


  16. 0
    Ronald Romero ·
    fellow PPers,

    I believe that even though i did most of my planning was up to three floors , planning for a skycraper from first floor up will almost be the same save for some variation in the design and use of the floor it will be typically a copy of the floor preceeding it .

    Am I right? So Charles send me a sample at ronnieksa@yahoo.com to learn some words, verbs and terminology planners are using when planning a skycrapper from ground up.

    Regards,

  17. 0
    Charleston-Joseph Orbe ·
    Ronald,

    The one I’m thinking of generating start design phase (concept, schematic, design development, contract documentation) Tender Phase, Construction Phase and Post Construction (defect liability period).

    The Skycraper I have in mind is the tallest in the Universe 1500 storey high above ground level (4,500 meters), compose of three towers (skycraper) within built up area (podium and retails).

  18. 0
    Sridhar J ·

    Its really exciting..

    Whats the Built up area you are planning for..

    & What is the FSI, Plinth area etc you are planning for..so that some conceptualisation can start off...

    Regards

    J Sridhar
  19. 0
    Luis Lombardo ·
    Hi Charles,

    Would you pls send me a copy too?
    Email: luis_lombardo@yahoo.com

    Thnks
    luigi
  20. 0
    Luis Lombardo ·
    Hi Charles,

    Would you pls send me a copy too?
    Email: luis_lombardo@yahoo.com

    Thnks
    luigi
  21. 0
    Armando Moriles ·
    Sensei,

    I really appreciate your idea and I would like to share any idea...

    To start with...

    1. If our building is 1,500 storeys excluding basements and podium and assuming a fast 5 day per floor structural works cycle using 5 complete form sets, etc...that would take us 7,500 calendar days;
    2. At 4,500 m high (14,760 feet) would be beyond air traffic height limitation. We may require sovereignty of our air space;
    3. I suggest we need a high altitude helicopter to do that;
    4. etc...


    Arman
  22. 0
    Abhay Gujrathi ·
    Hi Charles,

    Would you pls send me a copy too?
    Email: abhay.gujrathi@ril.com

    Thnks
    Abhay
  23. 0
    Chris Oggham ·
    Hi Arman,

    I found your post #22 extremely interesting, pointing out as it did the implausibility and impracticality of Charlie’s skyscraper. I’m sure it won’t be too long before Charlie responds with a detailed explanation of how to resolve all of the difficulties.

    I’m sure he’ll also get round to supplying the schedule that he promised to so many people as well, however, I won’t be holding my breath.

    Chris Oggham
  24. 0
    Akhtar Mehdi ·

    hiiiii  Could you pls send me

    hiiiii

     

     

    Could you pls send me the schedule for the high rise building at

     

    akhtarmehdi@hotmail.com

     

    Note : I am attending PMI -SP classes these days and learnt about this most usefull site during classes.

     

  25. 0
    Anning Sofi ·

    Ronald, 3 storey construction

    Ronald, 3 storey construction is not the same as highrise building construction.

    Why?  Among the many reasons, one of them, is logistic requirements... 

  26. 0
    Norodin Ulama ·

    none

    none

  27. 0
    Zoltan Palffy ·

    dig foundationspour

    dig foundations

    pour foundations

    set steel in basement

    set steel in lobby

    set steel 2nd floor and repeate for as many floor that you have 

    set roof steel

    set exterior skin and windows and repeate for as many floor that you have 

    fit out basement 

    fit out lobby 

    fit out 2nd floor and repeate for as many floor that you have 

    done 