Average S-Curve
In the Open Standard
Zq qzMember for 23 years 4 months
- Created
- 5
- 5
0
Is there any sofware that can create Average S-Curve (this is between Early and Late Dates curve" directly. Because some client is using this curve as a basis. What Im doing is extract this from primavera then plot it in excel. Primavera dont have this option. AM I CORRECT?