Milestone Planning

Erik JonkerMember for 23 years 6 months
Created
6
2
0
Is there ascheduling program that shows a series of milestones on a gantt bar?

This would make schedules much shorter.

Regards,

Erik

6 replies

Oldest first
  1. 0
    Vladimir Liberzon ·
    You can apply filters and hide everything except milestones - it is simple.
    You can move them to a special milestone phase and the phase bar will show all events. If you collapse this phase you will hide individual milestone bars.
    I don’t think that it is reasonable because you will hide also milestone descriptions.
    Regards,
    Vladimir
  2. 0
    Raj Maurya ·
    You can use MSP for the same by customising the field and show on the same line.If it is in limited number you can do in P3 also.
  3. 0
    Jaco Stadler ·
    Hi Erik
    I would suggest you look at a line of Balance I think you mean more than one milestone per line

    Cheers
  4. 0
    Vladimir Liberzon ·
    Jaco,
    do you use line of balance (we call them linear diagrams)?
    Vladimir
  5. 0
    David Bordoli ·
    You can, of course use Powerproject and put as many milestones, all coded differently if you wish, on the same line.

    David
  6. 0
    Philip Jonker ·
    Hi All,

    There was a programme, I have seen, I think it was artemis (I speak under correction), where you could resource a single activity with several resources, and use off-sets. These different resources would be represented by different colours or patterns on a single bar. I think this is the type of thing Erik is envisaging.

    Regards,

    Philip

Log in or join to reply