Planning books
In the Open Standard
BE
Bryan EleyMember for 19 years 6 months
- Created
- 59
- 10
0
I’m looking at starting a career as a Planner, before I start going through MS Projects and Sure Trak, I would like to read up on Critical Planning Analysis and not sure which books would be a good place to start, any recommendations would be appreciated?
Thanks,
Bryan.
59 replies
Oldest first- 0COCharleston-Joseph Orbe ·Hi Guys,
Be careful of this planning books.
I had a wonderful interview with super genius planner for a very high planning manager position.
Question: what is float?
My answer: Float is equal to LS - ES or LF - LF.
The genious was not satisfied. His expectation was the old way in defining float: The number of days that the project can be delayed without delaying the whole project.
Question: what if you have negative float. This happen when you constraints the project completion "must finish" and update the status of the project, generally the project is delay.
How can you imagine -260 days the project can be delayed without delaying the completion of the whole project.
Please advice!!
Cheers,
Charlie - 0VLVladimir Liberzon ·ES, LS, EF and LF usually are calculated without considering resource constraints. If the float is defined as the number of days (hours, seconds) an activity can be delayed without delaying the whole project it means that all constraints are taken into consideration including resource, financial and supply constraints. So this float may be not equal to LS - ES. Sometimes we cal it resource-constrained float.
- Delay is Acceleration. So -260 days float means that we need to shorten the duration by 260 days to be on time.
Actually I don’t like the concept of negative floats. I think that negative float means that there is no float or float is equal to zero. It corresponds with the definition - you cannot delay an activity without delaying project finish or violating time constraints. - 0PSPonnaganti Sridhar ·Hello to all,
even though iam a member of this site since from last 3 years, i had never dared to ask my questions on this site, since i think i am not so big as u all , and iam still in learing process.
Now yet i have a question, i don’t know wether i can ask or not,( may b am i fool in all your views by this question but iam dearing this time)if my question is a stupid or fault pls forgive me.
In my present project i had used two working calanders,
1.One with 7 days working days
2. 2nd with 6 days Working days
most of my activities are parked under Calander 1 and a few activites which are not related to constuction (Document) are parked under clander 2( while at the time of makeing the programme i though even the is construction going on a weekly off day on site , office work may not be there (this is the 1st time i done like this, this all happen because my the time i joined here in this company my P.M had done a programme in EXEL and told try to make similar and so when asked he told me told take all 7 days as working). the programme approved and it is going good, even though i had a little hikup in the 1st month.
here comes the actual problem, now the project is going on delay, since if i check with last (closing activity)of the schedule it is showing an -ve total float of -80day, which means an delay of 80days but if i check with the summary (over all summary on the top in the layout) it is showing an over all delay of -69 days , so i had given my report saying the project is being delayed by 69days, am i correct in this accept. if the consultant is going to ask iam thinking to show the reason of two clanders, but still iam not able to explane it properly and able to prepare my self.
can any any tell me am i correct
- 0RMRodel Marasigan ·Ponnaganti Sridhar,
Total float are calculated by LS-ES or LF-EF. On your closing activity may show -80 days but some of your activity are still positive float therefore your overall delay should be based on your project summary which you said -69 days. For you to check if you are correct, do a manual calculation based on your summary Late Start minus Early Start less non-working days if you are using 6 days plus holiday. For double check use Late Finish minus Early Finish less non working days.
Rodel - 0ASAhmed Syed ·Hi All
The best ever planning book I have found yet is listed below.
http://www.planningplanet.com/
Trust me here you get all REAL LIFE ISSUES not a bookish explaination of everything. Although, I have number of all kinds of planning books but, my first choice for seeking answer/guidence is this website.
Keep it up boys!!!!!!!!!!!!!
Cheers - 0DWDavid Watters ·Dennis Lock
Project Management
Generally a very good book, easily available on amazon, and relatively cheap. This was the guided reading for Project Management in my Mech Eng Degree, and a surprising number of people have a copy tucked away somewhere.
Alternatively, just have a bash ! It may not be easy, but CFD it aint ! - 0GGGaling Galing ·hi fellow project control engineers,
how are your project control job doing over there? i assume every thing is under control!
I have P3 experience but most projects here in usa are now into P5 transitioning into P6.
HELP, what i need is either manual or ref guide for p5/p6. you can send attached to my email.
thanks in advance for your help.
tony
tonypdg_20001@yahoo.com
U.S.A.
Log in or join to reply