Shift Work and Daylight Savings
In the Open Standard
Bernard ErtlMember for 23 years 10 months
- Created
- 1
- 3
0
For those of you associated with projects executing around the clock - with two 12 hour shifts (or three 8 hour shifts), what is the SOP (standard operating procedure) for handling the night shift during clock adjustments on daylight savings?
Ie. when jumping forward an hour, does the night shift stay on for the full shift even though it carries them an hour into the next shift? Do you simply adjust the clock hours that the shifts begin/end?
How do you manage this in your schedules, or is it not significant enough to worry about? Any discrepancy will be accounted for after a progress update post clock adjustment, but prior to the event, I suppose it could skew critical path schedules by an hour.
Bernard Ertl
eTaskMaker Project Planning Software
Ie. when jumping forward an hour, does the night shift stay on for the full shift even though it carries them an hour into the next shift? Do you simply adjust the clock hours that the shifts begin/end?
How do you manage this in your schedules, or is it not significant enough to worry about? Any discrepancy will be accounted for after a progress update post clock adjustment, but prior to the event, I suppose it could skew critical path schedules by an hour.
Bernard Ertl
eTaskMaker Project Planning Software
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?