Planning in Pakistan

Jason FrostMember for 21 years 1 month
Created
5
2
0
I am looking currently looking at a project in Pakistan and have no idea as to the skill/expertise of the contractors in this country.

The project consists of several 35+ storey buildings of mixed use sitting on a podium car park.

Could anyone advise me on

1) The contracors within Pakistan with the expertise to complete this project

2) The type of construction generally used for high rise ie Steel, Concrete or hybrid

3) Typical cycle time per floor

Jason

5 replies

Oldest first
  1. 0
    Shahzad Munawar ·
    I think you are coming from Al Habtoor Group for their project in Islamabad.

    There are different contractors in Pakistan who have ability to complete such type of structures but limited to 15~25 stories at best.

    Completion period for one Floor is from 20~30 days.

  2. 0
    Jason Frost ·
    Thanks Shahzad,

    Unfortunately it is not that job in Islamabad but rather Karachi.

    Jason
  3. 0
    Zhang Haixiang ·
    i have no idea of this kind of buiding.
    I think you can find good contractor there.
    We have built a nuclear powerplant there, most of the civil works are done by local contractor.
  4. 0
    Kashif Hussain Farooqui ·
    I am working in Karachi, Pakistan as a planning engineer for multi-story building project having 12 buildings each ground + 17 floors. The project is being awarded to top contractors of the country :
    1. Associated Constructors Pvt. Ltd
    2. Habib Rafiq Pvt. Ltd.
    3. Builders Associates Pvt. LTd.

    The floor cycle we have achieved so far, varies from 15 days to 22 days depending on the formwork system. Completion period of one floor is about 26 days. Structure work is in progress.

    If you need any more information, please don’t hesitate to send e-mail to kashifstudy@yaoo.com

    Thanks,
    Kashif Farooqui
    Planning Engineer
  5. 0
    Shahab Ali ·
    Top listed contractors in pakistan

    1)Descon Engineering limited
    2)Habib Rafique
    3)SKB
    4)Sachel
    5)Chinese............compnies i.e on mangla etc
    6)Italian...........compies...i.e impregilio...

    If u need some, u can ask me..

    regards,

    Shahab