Standard Manhours for Isometric Drw
In the Open Standard
Norzul IbrahimMember for 20 years 10 months
- Created
- 0
- 2
0
Hi Guys,
Would appreciate your advise on the typical manhours required to prepare an isometric drw. Was told by our consultant that the industry (oil&gas) standard manhour for preparing one isometric drw is about 15-20 hrs.
Fyi, we generate the iso from the electronic 3D model (Integraph PDS 3D software). Let say if we require 1000 iso drws, then the total hours is 20,000. From this we could estimate the manpower required for the job.
Thanks
norzul
Would appreciate your advise on the typical manhours required to prepare an isometric drw. Was told by our consultant that the industry (oil&gas) standard manhour for preparing one isometric drw is about 15-20 hrs.
Fyi, we generate the iso from the electronic 3D model (Integraph PDS 3D software). Let say if we require 1000 iso drws, then the total hours is 20,000. From this we could estimate the manpower required for the job.
Thanks
norzul
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?