Methods of Monitoring progress
In the Open Standard
Andrew OwensonMember for 20 years 11 months
- Created
- 52
- 11
0
Guys
What is the best method of monitoring progress ?
I use three methods
1) Static progress - where you update the bars with % complete only and draw a line from the progress date to indicate position on programme.
2) Critical path - where I update the actual starts etc as well as % complete. I also baseline the project to give a comparison.
3) Planned versus actual "S" curves
I use MSP for the first two and export the data to Excel for the last one
Andrew
What is the best method of monitoring progress ?
I use three methods
1) Static progress - where you update the bars with % complete only and draw a line from the progress date to indicate position on programme.
2) Critical path - where I update the actual starts etc as well as % complete. I also baseline the project to give a comparison.
3) Planned versus actual "S" curves
I use MSP for the first two and export the data to Excel for the last one
Andrew
52 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?