Methods of Monitoring progress

Andrew OwensonMember for 20 years 11 months
Created
52
11
0
Guys

What is the best method of monitoring progress ?

I use three methods

1) Static progress - where you update the bars with % complete only and draw a line from the progress date to indicate position on programme.

2) Critical path - where I update the actual starts etc as well as % complete. I also baseline the project to give a comparison.

3) Planned versus actual "S" curves

I use MSP for the first two and export the data to Excel for the last one

Andrew

52 replies

Oldest first
  1. 0
    Jaga deesan ·

    Dear All,Better Progress

    Dear All,

    Better Progress Measurement concept is given in a simple and clear manner in the following YouTube Link, which may be of your interest.

    UCJ1QCqXRumD34CFwYPb1dmw

    Regards,

    R. Jagadeesan

  2. 0
    Zoltan Palffy ·

    I beleive that Edgar was the

    I beleive that Edgar was the first to comment and S-Curves and EVM are stil relevant. 

    not sure what you want to use ? 