1. How to best calculate productivity rate of a construction activity?

2. Why there is no productivity rate column in P3 or MSP?

Ragards
frans

4 replies

Oldest first
  1. 0
    Vladimir Liberzon ·
    Frans,
    if you want to use productivities in schedule development try Spider Project (Demo can be downloaded from http://www.spiderproject.ru/spider_e.php).
    In this package you can assign productivities manually or create Productivity database and use it in all projects of the organization.
    I don’t know why work quantities and resource productivities are not supported by other software packages.
    Regards,
    Vladimir
  2. 0
    Mohammed Mujtaba ·
    Can any one tell the specific formula for calculating productivity.
  3. 0
    Vladimir Liberzon ·
    Productivity may be measured as the quantity of work per one hour, or as quantity of work hourd per one unit of work quantity.

    Best Regards,
    Vladimir
  4. 0
    Shah. HB ·
    Productivity rate = [Work quantity/{activity duration * resource usage}]

Log in or join to reply