weightage

Anshad NKMember for 20 years 5 months
Created
1
2
0
Hay everybody

what are the ways to take the weightage for the deliverables in a project?


1 reply

Oldest first
  1. 0
    Suraj Bhatt ·
    A good way is to assign weightage based on budgeted cost as u may be using it as a parameter for progress.
    Regards,
    Suraj