Level 3, 4 & 5 planning.

Neil BraniganMember for 19 years 10 months
Created
5
2
0
To all planners,

Being a rookie in the business, could anyone please educate me on the distinct differences between level 3, 4 & 5 planning. My belief is that level 3 is planning at a WBS level. Planning with activities below this - 5-10 approx. will be level 4 and level 5 is very detailed planning.
Could anyone please point me in the right direction on this one, please?

Cheers
Neil

5 replies

Oldest first
  1. 0
    Nigel Winkley ·
    Neil

    If you have a look here, for an article by Gary France entitled "Standards for the Levels of a Programme or Schedule" it may help you.

    http://www.planningengineers.org/publications/papers.aspx

    Cheers

    Nige
  2. 0
    James Griffiths ·
    Hi Neil,

    Each WBS "level" is an increase in the amount of detail which an activity is sub-divided or grouped (if that makes any sense). A "level" is based on a WBS chart, where any group summary name that resides on the same row is also on the same "level". Each subsequent row of names equates to a new "level". Example:

    L1 = CAR
    L2 = Mechanical Electrical
    L3 = ENGINE,BODY ECU, INSTRUMENTS
    L4 = Further subdivisions of each component.


    The number of "levels" that you have is wholly dependent upon how how many groupings and sub-groupings you wish to include by the time you reach the individual deliverable. However, you can execute a project and plan a project at any desired level. But the higher the level (3,4,5 ish), the less detail and definition is contained within the activity description. As a rough guide, you are correct in that, down to level 4/5, the activities may be poorly defined. Level 10 is probably excessively detailed.

    HTH

    James.
  3. 0
    Rommel Ramirez ·
    Guys,

    L1 = Overall Project Master Programme
    L2 = Summary Programme
    a. design
    b. production or construction
    c. procurement
    L3 = Detail Progamme
    a. design
    b. production or construction
    c. procurement
    L4 = Specific/Constraints Term
    L5 = Subcontractors own Detailed Programme

    Mabuhay!!!
    Rommel
  4. 0
    Eugene K ·
    yes. i also find this classification of L1, L2.. L5 schedule very vague. the most "defined" classifaction i hv come across was this;

    L1: (Owner’s) Development Programme (probably each project/subproj represented by 1 bar)
    L2: L1 + Design/Procurement + Construction detail to major discipline
    L3: (Contractor’s) Construction Programme = L2 + Construction detail to floor/area/zone, and trade/system
    L4: (Contractor’s) Monthly Programme = Extract of L3 for 3 months (1 + 2 months Lookahead), detail to weekly work plan for current month.
    L5: (Contractor’s) Weekly Programme = Extract of L4 for the month, detail to daily site work plan for current week.

    I find this classification suitably definitive, the only thing i m not sure is... as a contractor preparing L3...
    must we incorporate the the monthly details of L4 and weekly details of L5 into the L3?

    Any ideas guys?
  5. 0
    D Artagnan ·

    PEO has already shut

    PEO has already shut down....i wish i had those papers

Log in or join to reply