REFERENCE PLANNING FOR EPC PIPELINE PROJECTS

Sanjeev KoulMember for 19 years 8 months
Created
4
27
0
I have been assigned to prepare a masterplan for EPC pipeline project , starting from feasibility study , engineering , formation and award of EPC contracts,procurement,constructioin/installation , testing and commisioning of pipeline.
I am in need of a sample pipeline project schedule (ie P3 schedule) detailing list of activities (civil,mechanical,piping,instrumentation,electrical etc), durations of activities ,critical activities etc.I need support till i complete this schedule on P3 espacially as i have very limited and basic knowledge only about Primavera.
I shall highly appreciate any aupport in this connection.

4 replies

Oldest first
  1. 0
    Krishnamurhi Ramasubbu ·
    Sanjeev,

    Please find below the major activities for a Pipeline Project. You need to add or delete to suit your requirements


    Concept Study (CSR):
    Preparation of BFD
    Basis for the study
    Scope of Work
    Site Visits & Data Collections
    Prepare Deliverables
    Prepare company estimate
    Prepare EPC Tender doc.
    Prepare commercial part of EPC doc
    Integrate Commercial & Tech parts of Tender
    Bidding period
    Bid clarification & evaluation
    Receipt of Commercial Bid
    Obtain Approval Of Tender Board
    Prepare Award Recommendation
    Award of EPC Contract
    Kick-off Meeting
    Site Establishments/Camp const/manpower/eqpt mobilisation

    Engineering
    Pipeline
    Site Survey - Pipelines
    Overall / Unit Plot Plans - Prepare/ Issue/ Review
    Wall thickness / Material Selection Reports- Prepare/Issue/Approve
    Piping Key Plans
    Piping Isometrics
    Pipeline Route Alignment Sheets / Other Dwgs- Prepare/Issue/AFC
    Procurement
    Line Pipes / valves / flanges & fittings / Electrical items ? Cathodic Protection
    Issue Specs
    Float Enquiry
    Receipt of Offers
    Technical Recommendations
    MR and PO Placement
    Receipt of Vendor Dwgs for Approval
    Vendor Dwgs Approval
    Mfg & Site Del
    Construction
    ROW
    Trench Excavation
    Trench Cleaning
    Collection of Sand Padding Material
    Pre Padding
    Pipeline Stringing
    Cutting, edge preparation, bending
    Alignment / Welding
    NDT (Above Ground)
    Joint Coating (Above Ground)
    Lowering
    Tie In
    Post Pading
    Back Filling , Windrow
    Pigging/Cleaning/Gauging/Hydrotesting
    Dewatering & drying
    Installation of Marker Posts
    Installation of CP System


    Cheers
  2. 0
    Sanjeev Koul ·
    hi Mr Krishnamurhi ;
    Thanks for ur valuable guidance but i need a detailed subactivity breakdown as in a P3 programme.Brekdown should cover civil , mech , elect , inst for pipeline and stations ; activity duration ;and clearly list out the critical activities in the sample P3 programme.
  3. 0
    Jesse Liu ·
    I hope this can help. It’s includes all the WBS & activities of my previous project. The critical activities is calculated by P3. I can’t do everything for you or next time you will ask me to wipe you ass!
    WBS Linked Activities
    WBS Code WBS Name
    XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX Corporation
    XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX-Branch
    OIL Oil Projects
    Unkown Project Unkown Project Name
    PS#6 Pump Station No. 6 Change Orders No.1-No.4
    GASSAB FSF GASSAB FSF Project
    4 Buildings 4 Buildings
    NFPF GREATER NEEM FPF PROJECT
    NFPF.01 PROJECT MAJOR MILESTONES
    M110 Contract Effective Date
    M120 Site Mobilization Completion Date
    M130 Mechanical Completion Date
    M140 Provisional Acceptance Date
    NFPF.02 ENGINEERING
    NFPF.02.01 FPF
    NFPF.02.01.01 General
    E11010 Site visit, data collection & S/V report
    E11020 Design basis mamorandum
    E11030 PFDs and P&IDs
    E11040 Process simulation/calculations
    E11050 SLD’s & motor feeder schematics
    E11060 Overall I&C system block diagram
    E11070 Plot plan & key plans
    E11080 Simulation / material balance report
    E11090 O&C philosophy
    E11100 Finalization of key deliverables
    E11170 Major engineering completed
    NFPF.02.01.02 Process
    E11110 Optimisation studies
    E11120 Equipment list / line list
    E11130 HAZOP
    E11140 HAZOP reports & close-outs
    E11150 Miscellaneous process drawings
    E11160 Pre-com./commissioning manuals
    NFPF.02.01.03 Piping
    NFPF.02.01.03.01 Engineering
    E13130 Data sheets & specifications
    E13140 Equipment layouts & piping GA’s
    E13150 Stress analysis, Iso’s & Std drawings
    E13160 Misc.piping drawings/details
    E13170 Bulk MTO’s
    NFPF.02.01.03.02 Procurement Service
    E13010 MR PIP001 for Valves
    E13020 MR PIP003 for U/G Pipes & Fittings
    E13030 MR PIP004 for Insulation
    E13040 MR PIP005A for Flexible Hoses
    E13050 MR PIP005B for Access Fittings
    E13060 MR PIP005C for Basket Strainer
    E13070 MR PIP005D for Y Type Strainer
    E13080 MR PIP005E for Flame Arrestor
    E13090 MR PIP005F for Expansion Bellow
    E13100 MR PIP006 for A/G Pipes and Fittings
    E13110 MR PIP008 for Painting
    E13120 MR PIP009 for Fire Fighting Equipment
    E13180 Technical bid evaluation
    NFPF.02.01.04 Mechanical
    NFPF.02.01.04.01 Engineering
    E14240 Mechanical spec. & data sheets
    E14250 Tanks fabrication drawings
    E14260 Misc. mechanical drawings / details
    NFPF.02.01.04.02 Procurement Service
    E14010 MR-001 for FWKO
    E14020 MR-002 for Test Separator
    E14030 MR-003 for Heater Treaters
    E14040 MR-004 for CPI Separator
    E14050 MR-005 for Gas Boot
    E14060 MR-006 for Diesel Fuel Coalescing Separtor Filt.
    E14070 MR-007 for Flare Stack
    E14080 MR-008 for Portable Water Treatment Package
    E14090 MR-009 for Flare KO Drum
    E14100 MR-010 for Floating Oil Skimmer
    E14110 M011 for Fuel Gas Scrubber
    E14120 M012 for Chemical Injection Skid
    E14130 M013 for Closed Drain Sump Skid
    E14140 M014 for Instrument Air Package
    E14150 M015 for Nitrogen Generation Package
    E14160 M016 for Heat Exchangers
    E14170 M017 for Centrifugal Pumps
    E14180 M018 for Screw Pumps
    E14190 MR for Progressive Cavity Pumps
    E14200 MR for Fire Extinguishers
    E14210 MR for Gear Pumps
    E14220 MR-025 for API Tank Material
    E14230 MR-026 for API Tank Accessories
    E14270 Technical bid evaluation
    NFPF.02.01.05 Electrical
    NFPF.02.01.05.01 Engineering
    E15140 Specifications & data sheets
    E15150 Load list, SLD’s & calculations
    E15160 Electrical layouts, schedules, HACs
    E15170 Std installation Dtls & interconnection
    E15180 Misc. electrical drawings / details
    E15190 Electrical bulk MTO
    NFPF.02.01.05.02 Procurement Service
    E15010 MR-001 for 6.6KV Switchgear
    E15020 MR-002 for 33KV Switchgear at Substation
    E15030 MR-003 for Power Transformers
    E15040 MR-004 for 400V Switchgear/Busducts
    E15050 MR-005 for Diesel Generator Set
    E15060 MR-006 for Electric Heaters
    E15070 MR-007 for AC UPS System
    E15080 MR-008 for DC UPS System
    E15090 MR-009 for Lighting Poles & Junction Boxes
    E15100 MR-010 for Cables,Glands & Termination Kits
    E15110 MR-011 for Cable Trays and Accessories
    E15120 MR-012 for Electrical Bulks
    E15130 MR-013 for Electric Heat Tracing
    E15200 Technical bid evaluation
    NFPF.02.01.06 Cathodic Protection
    NFPF.02.01.06.01 Engineering
    E16040 CP specs & calculations
    E16050 CP design deliverables
    E16060 Misc. CP drawings/details
    E16070 CP preliminary MTO
    NFPF.02.01.06.02 Procurement Service
    E16010 MR for CP Materials under Tank Bottom
    E16020 MR for CP Material for Pilings
    E16030 MR for Aluminum Alloy Sacrifial Anode
    E16080 Technical bid evaluation
    NFPF.02.01.07 Instrumentation & Control
    NFPF.02.01.07.01 Engineering
    E17160 Instrument specs & data sheets
    E17170 Control system Arch.,control & logic
    E17180 Inst.index,schedules,C&E Dgm
    E17190 Control room layout & instrument
    E17200 F&G system drawings
    E17210 Loop /hook-up / interconnection
    E17220 Misc.instrument drawings/details
    E17230 Instrument bulk MTO
    NFPF.02.01.07.02 Procurement Service
    E17010 MR J001 for ESDV
    E17020 MR J002 for CV & PCV
    E17030 MR J003 for PSV & PVRV
    E17040 MR J004 for Electronic Transmitters
    E17050 MR J005 for Level Transmitters
    E17060 MR J006 for Flow Meter
    E17070 MR J007 for Gauges
    E17080 MR J008 for FE (Orifice Plates) & RO
    E17090 MR J009 for Product Allocation Metering Skid
    E17100 MR J010 for Control / Safety System
    E17110 MR J011 for Fire & Gas Detection Devices
    E17120 MR J012 for Building Fire Alarm System
    E17130 MR J013 for Instrument Cables & Glands
    E17140 MR J014 for Instrument Junction Boxes
    E17150 MR J015 for Instrument Bulks
    E17240 Technical bid evaluation
    NFPF.02.01.08 Civil
    NFPF.02.01.08.01 Engineering
    E18080 Topographical/geotechnical survey spec
    E18090 Civil/structural general notes,typical dwg.
    E18100 Typical tank pad details
    E18110 Rough grading plans,pile key plan
    E18120 Final grading,pile lyt,skid/misc.
    E18130 Structural steel/pipe rack/support
    E18140 Misc.civil drawings/details
    NFPF.02.01.08.02 Procurement Service
    E18010 MR for Piling material
    E18020 MR for Structual Steel
    E18030 MR for Fencing material
    E18040 MR for Building material
    E18050 MR for Concrete material
    E18060 MR for Civil specialty items
    E18070 MR for Culverts material
    NFPF.02.02 33KV Substation
    NFPF.02.02.01 Electrical
    E18150 Data sheet
    E18160 Feeder list & single line diagram
    E18170 Electrical layouts
    E18180 Haz.area classification / safety data
    E18190 Misc. electrical drawings / details
    NFPF.02.02.02 Cathodic Protection
    E18200 CP design deliverables
    NFPF.02.02.03 Instrumentation & Control
    E18210 Instrumen cable block diagram
    E18220 Instrument interconnection drawing
    E18230 Miscellaneous drawings/documents
    NFPF.02.02.04 Civil
    E18240 Spec. for top/geotech survey
    E18250 Fence layouts & gate details
    E18260 Rough grading plan & piling key plan
    E18270 Design calculations
    E18280 Final grading plans & pile layouts
    E18290 Civil / structural layouts & details
    E18300 Misc.civil drawings / details
    NFPF.03 PROCUREMENT
    NFPF.03.01 Mechanical
    NFPF.03.01.01 Free Water Knock Out Drum(M-001)
    P10010 Issue of inquires
    P10020 Issue of purchase order
    P10030 Delivery Ex-Works
    P10040 Transportation to Sudan
    P10050 Custom Clearance
    P10060 Delivery job site
    P10070 Required on Site (ROS) date
    NFPF.03.01.02 Test Separator(M-002)
    P10090 Issue of inquires
    P10100 Issue of purchase order
    P10110 Delivery Ex-Works
    P10120 Transportation to Sudan
    P10130 Custom Clearance
    P10140 Delivery job site
    P10150 Required on Site (ROS) date
    NFPF.03.01.03 Heater Treater (M-003)
    P10170 Issue of inquires
    P10180 Issue of purchase order
    P10190 Delivery Ex-Works
    P10200 Transportation to Sudan
    P10210 Custom Clearance
    P10220 Delivery job site
    P10230 Required on Site (ROS) date
    NFPF.03.01.04 CPI Separator(M-004)
    P10250 Issue of inquires
    P10260 Issue of purchase order
    P10270 Delivery Ex-Works
    P10280 Transportation to Sudan
    P10290 Custom Clearance
    P10300 Delivery job site
    P10310 Required on Site (ROS) date
    NFPF.03.01.05 Gas Boot(M-005)
    P10330 Issue of inquires
    P10340 Issue of purchase order
    P10350 Delivery Ex-Works
    P10360 Transportation to Sudan
    P10370 Custom Clearance
    P10380 Delivery job site
    P10390 Required on Site (ROS) date
    NFPF.03.01.06 Diesel Fuel Coalescing Separator Filter(M-006)
    P10410 Issue of inquires
    P10420 Issue of purchase order
    P10430 Delivery Ex-Works
    P10440 Transportation to Sudan
    P10450 Custom Clearance
    P10460 Delivery job site
    P10470 Required on Site (ROS) date
    NFPF.03.01.07 Flare Stack(M-007)
    P10490 Issue of inquires
    P10500 Issue of purchase order
    P10510 Delivery Ex-Works
    P10520 Transportation to Sudan
    P10530 Custom Clearance
    P10540 Delivery job site
    P10550 Required on Site (ROS) date
    NFPF.03.01.08 Portable Water Treatment Package(M-008)
    P10570 Issue of inquires
    P10580 Issue of purchase order
    P10590 Delivery Ex-Works
    P10600 Transportation to Sudan
    P10610 Custom Clearance
    P10620 Delivery job site
    P10630 Required on Site (ROS) date
    NFPF.03.01.09 Flare KO Drum(M-009)
    P10650 Issue of inquires
    P10660 Issue of purchase order
    P10670 Delivery Ex-Works
    P10680 Transportation to Sudan
    P10690 Custom Clearance
    P10700 Delivery job site
    P10710 Required on Site (ROS) date
    NFPF.03.01.10 Floating Oil Skimmer(M-010)
    P10730 Issue of inquires
    P10740 Issue of purchase order
    P10750 Delivery Ex-Works
    P10760 Transportation to Sudan
    P10770 Custom Clearance
    P10780 Delivery job site
    P10790 Required on Site (ROS) date
    NFPF.03.01.11 Fuel Gas Scrubber(M-011)
    P10810 Issue of inquires
    P10820 Issue of purchase order
    P10830 Delivery Ex-Works
    P10840 Transportation to Sudan
    P10850 Custom Clearance
    P10860 Delivery job site
    P10870 Required on Site (ROS) date
    NFPF.03.01.12 Chemical Injection Skid(M-012)
    P10890 Issue of inquires
    P10900 Issue of purchase order
    P10910 Delivery Ex-Works
    P10920 Transportation to Sudan
    P10930 Custom Clearance
    P10940 Delivery job site
    P10950 Required on Site (ROS) date
    NFPF.03.01.13 Closded Drain Sump Skid(M-013)
    P10970 Issue of inquires
    P10980 Issue of purchase order
    P10990 Delivery Ex-Works
    P11000 Transportation to Sudan
    P11010 Custom Clearance
    P11020 Delivery job site
    P11030 Required on Site (ROS) date
    NFPF.03.01.14 Instrument Air Package(M-014)
    P11050 Issue of inquires
    P11060 Issue of purchase order
    P11070 Delivery Ex-Works
    P11080 Transportation to Sudan
    P11090 Custom Clearance
    P11100 Delivery job site
    P11110 Required on Site (ROS) date
    NFPF.03.01.15 Nitrogen Generation Package(M-015)
    P11130 Issue of inquires
    P11140 Issue of purchase order
    P11150 Delivery Ex-Works
    P11160 Transportation to Sudan
    P11170 Custom Clearance
    P11180 Delivery job site
    P11190 Required on Site (ROS) date
    NFPF.03.01.16 Heat Exchangers(M-016)
    P11210 Issue of inquires
    P11220 Issue of purchase order
    P11230 Delivery Ex-Works
    P11240 Transportation to Sudan
    P11250 Custom Clearance
    P11260 Delivery job site
    P11270 Required on Site (ROS) date
    NFPF.03.01.17 Centrifugal Pumps(M-017)
    P11290 Issue of inquires
    P11300 Issue of purchase order
    P11310 Delivery Ex-Works
    P11320 Transportation to Sudan
    P11330 Custom Clearance
    P11340 Delivery job site
    P11350 Required on Site (ROS) date
    NFPF.03.01.18 Screw Pumps(M-018)
    P11370 Issue of inquires
    P11380 Issue of purchase order
    P11390 Delivery Ex-Works
    P11400 Transportation to Sudan
    P11410 Custom Clearance
    P11420 Delivery job site
    P11430 Required on Site (ROS) date
    NFPF.03.01.19 Progressive Cavity Pumps
    P11450 Issue of inquires
    P11460 Issue of purchase order
    P11470 Delivery Ex-Works
    P11480 Transportation to Sudan
    P11490 Custom Clearance
    P11500 Delivery job site
    P11510 Required on Site (ROS) date
    NFPF.03.01.20 Fire Extinguishers
    P11530 Issue of inquires
    P11540 Issue of purchase order
    P11550 Delivery Ex-Works
    P11560 Transportation to Sudan
    P11570 Custom Clearance
    P11580 Delivery job site
    P11590 Required on Site (ROS) date
    NFPF.03.01.21 Gear Pumps(M-023)
    P11610 Issue of inquires
    P11620 Issue of purchase order
    P11630 Delivery Ex-Works
    P11640 Transportation to Sudan
    P11650 Custom Clearance
    P11660 Delivery job site
    P11670 Required on Site (ROS) date
    NFPF.03.01.22 API Tank Materials(M-025)
    P11690 Issue of inquires
    P11700 Issue of purchase order
    P11710 Delivery Ex-Works
    P11720 Transportation to Sudan
    P11730 Custom Clearance
    P11740 Delivery job site
    P11750 Required on Site (ROS) date
    NFPF.03.01.23 API Tank Accessories(M-026)
    P11770 Issue of inquires
    P11780 Issue of purchase order
    P11790 Delivery Ex-Works
    P11800 Transportation to Sudan
    P11810 Custom Clearance
    P11820 Delivery job site
    P11830 Required on Site (ROS) date
    NFPF.03.02 Instrumentation
    NFPF.03.02.01 ESDV (J001)
    P11850 Issue of inquires
    P11860 Issue of purchase order
    P11870 Delivery Ex-Works
    P11880 Transportation to Sudan
    P11890 Custom Clearance
    P11900 Delivery job site
    P11910 Required on Site (ROS) date
    NFPF.03.02.02 CV & PCV (J002)
    P11930 Issue of inquires
    P11940 Issue of purchase order
    P11950 Delivery Ex-Works
    P11960 Transportation to Sudan
    P11970 Custom Clearance
    P11980 Delivery job site
    P11990 Required on Site (ROS) date
    NFPF.03.02.03 PSV & PVRV (J003)
    P12010 Issue of inquires
    P12020 Issue of purchase order
    P12030 Delivery Ex-Works
    P12040 Transportation to Sudan
    P12050 Custom Clearance
    P12060 Delivery job site
    P12070 Required on Site (ROS) date
    NFPF.03.02.04 Electronic Transmitters (J004)
    P12090 Issue of inquires
    P12100 Issue of purchase order
    P12110 Delivery Ex-Works
    P12120 Transportation to Sudan
    P12130 Custom Clearance
    P12140 Delivery job site
    P12150 Required on Site (ROS) date
    NFPF.03.02.05 Level Transmitters (J005)
    P12170 Issue of inquires
    P12180 Issue of purchase order
    P12190 Delivery Ex-Works
    P12200 Transportation to Sudan
    P12210 Custom Clearance
    P12220 Delivery job site
    P12230 Required on Site (ROS) date
    NFPF.03.02.06 Flow Meters (J006)
    P12250 Issue of inquires
    P12260 Issue of purchase order
    P12270 Delivery Ex-Works
    P12280 Transportation to Sudan
    P12290 Custom Clearance
    P12300 Delivery job site
    P12310 Required on Site (ROS) date
    NFPF.03.02.07 Gauges (J007)
    P12330 Issue of inquires
    P12340 Issue of purchase order
    P12350 Delivery Ex-Works
    P12360 Transportation to Sudan
    P12370 Custom Clearance
    P12380 Delivery job site
    P12390 Required on Site (ROS) date
    NFPF.03.02.08 FE (Orifice Plates) & RO (J008)
    P12410 Issue of inquires
    P12420 Issue of purchase order
    P12430 Delivery Ex-Works
    P12440 Transportation to Sudan
    P12450 Custom Clearance
    P12460 Delivery job site
    P12470 Required on Site (ROS) date
    NFPF.03.02.09 Product Allocation Metering Skid (J009)
    P12490 Issue of inquires
    P12500 Issue of purchase order
    P12510 Delivery Ex-Works
    P12520 Transportation to Sudan
    P12530 Custom Clearance
    P12540 Delivery job site
    P12550 Required on Site (ROS) date
    NFPF.03.02.10 Control System / Safety System (J010)
    P12570 Issue of inquires
    P12580 Issue of purchase order
    P12590 Delivery Ex-Works
    P12600 Transportation to Sudan
    P12610 Custom Clearance
    P12620 Delivery job site
    P12630 Required on Site (ROS) date
    NFPF.03.02.11 Fire & Gas Detection Devices (J011)
    P12650 Issue of inquires
    P12660 Issue of purchase order
    P12670 Delivery Ex-Works
    P12680 Transportation to Sudan
    P12690 Custom Clearance
    P12700 Delivery job site
    P12710 Required on Site (ROS) date
    NFPF.03.02.12 Building Fire Alarm System (J012)
    P12730 Issue of inquires
    P12740 Issue of purchase order
    P12750 Delivery Ex-Works
    P12760 Transportation to Sudan
    P12770 Custom Clearance
    P12780 Delivery job site
    P12790 Required on Site (ROS) date
    NFPF.03.02.13 Instrument Cables & Glands (J013)
    P12810 Issue of inquires
    P12820 Issue of purchase order
    P12830 Delivery Ex-Works
    P12840 Transportation to Sudan
    P12850 Custom Clearance
    P12860 Delivery job site
    P12870 Required on Site (ROS) date
    NFPF.03.02.14 Instrument Junction Boxes (J014)
    P12890 Issue of inquires
    P12900 Issue of purchase order
    P12910 Delivery Ex-Works
    P12920 Transportation to Sudan
    P12930 Custom Clearance
    P12940 Delivery job site
    P12950 Required on Site (ROS) date
    NFPF.03.02.15 Instrument Bulk Materials (J015)
    P12970 Issue of inquires
    P12980 Issue of purchase order
    P12990 Delivery Ex-Works
    P13000 Transportation to Sudan
    P13010 Custom Clearance
    P13020 Delivery job site
    P13030 Required on Site (ROS) date
    NFPF.03.03 Electrical
    NFPF.03.03.01 6.6KV Switchgear (E001)
    P13050 Issue of inquires
    P13060 Issue of purchase order
    P13070 Delivery Ex-Works
    P13080 Transportation to Sudan
    P13090 Custom Clearance
    P13100 Delivery job site
    P13110 Required on Site (ROS) date
    NFPF.03.03.02 Power Transformers (E003)
    P13130 Issue of inquires
    P13140 Issue of purchase order
    P13150 Delivery Ex-Works
    P13160 Transportation to Sudan
    P13170 Custom Clearance
    P13180 Delivery job site
    P13190 Required on Site (ROS) date
    NFPF.03.03.03 400V Switchgear / Busducts(E004)
    P13210 Issue of inquires
    P13220 Issue of purchase order
    P13230 Delivery Ex-Works
    P13240 Transportation to Sudan
    P13250 Custom Clearance
    P13260 Delivery job site
    P13270 Required on Site (ROS) date
    NFPF.03.03.04 Diesel Generator Set (E005)
    P13290 Issue of inquires
    P13300 Issue of purchase order
    P13310 Delivery Ex-Works
    P13320 Transportation to Sudan
    P13330 Custom Clearance
    P13340 Delivery job site
    P13350 Required on Site (ROS) date
    NFPF.03.03.05 Electric Heaters (E006)
    P13370 Issue of inquires
    P13380 Issue of purchase order
    P13390 Delivery Ex-Works
    P13400 Transportation to Sudan
    P13410 Custom Clearance
    P13420 Delivery job site
    P13430 Required on Site (ROS) date
    NFPF.03.03.06 AC UPS System (E007)
    P13450 Issue of inquires
    P13460 Issue of purchase order
    P13470 Delivery Ex-Works
    P13480 Transportation to Sudan
    P13490 Custom Clearance
    P13500 Delivery job site
    P13510 Required on Site (ROS) date
    NFPF.03.03.07 DC UPS System (E008)
    P13530 Issue of inquires
    P13540 Issue of purchase order
    P13550 Delivery Ex-Works
    P13560 Transportation to Sudan
    P13570 Custom Clearance
    P13580 Delivery job site
    P13590 Required on Site (ROS) date
    NFPF.03.03.08 Lighting Poles & Junction Boxes (E009)
    P13610 Issue of inquires
    P13620 Issue of purchase order
    P13630 Delivery Ex-Works
    P13640 Transportation to Sudan
    P13650 Custom Clearance
    P13660 Delivery job site
    P13670 Required on Site (ROS) date
    NFPF.03.03.09 Cables, Glands & Termination Kits (E010)
    P13690 Issue of inquires
    P13700 Issue of purchase order
    P13710 Delivery Ex-Works
    P13720 Transportation to Sudan
    P13730 Custom Clearance
    P13740 Delivery job site
    P13750 Required on Site (ROS) date
    NFPF.03.03.10 Cable Trays and Accessories (E011)
    P13770 Issue of inquires
    P13780 Issue of purchase order
    P13790 Delivery Ex-Works
    P13800 Transportation to Sudan
    P13810 Custom Clearance
    P13820 Delivery job site
    P13830 Required on Site (ROS) date
    NFPF.03.03.11 Electrical Bulk Materials (E012)
    P13850 Issue of inquires
    P13860 Issue of purchase order
    P13870 Delivery Ex-Works
    P13880 Transportation to Sudan
    P13890 Custom Clearance
    P13900 Delivery job site
    P13910 Required on Site (ROS) date
    NFPF.03.03.12 Electrical Heat Tracing (E013)
    P13930 Issue of inquires
    P13940 Issue of purchase order
    P13950 Delivery Ex-Works
    P13960 Transportation to Sudan
    P13970 Custom Clearance
    P13980 Delivery job site
    P13990 Required on Site (ROS) date
    NFPF.03.03.13 33KV Switchgear at Power Station (E002)
    P14010 Issue of inquires
    P14020 Issue of purchase order
    P14030 Delivery Ex-Works
    P14040 Transportation to Sudan
    P14050 Custom Clearance
    P14060 Delivery job site
    P14070 Required on Site (ROS) date
    NFPF.03.04 Piping
    NFPF.03.04.01 Valves (PIP001)
    P14090 Issue of inquires
    P14100 Issue of purchase order
    P14110 Delivery Ex-Works
    P14120 Transportation to Sudan
    P14130 Custom Clearance
    P14140 Delivery job site
    P14150 Required on Site (ROS) date
    NFPF.03.04.02 U/G Pipes & Fittings (PIP003)
    P14170 Issue of inquires
    P14180 Issue of purchase order
    P14190 Delivery Ex-Works
    P14200 Transportation to Sudan
    P14210 Custom Clearance
    P14220 Delivery job site
    P14230 Required on Site (ROS) date
    NFPF.03.04.03 Insulation Materials (PIP004)
    P14250 Issue of inquires
    P14260 Issue of purchase order
    P14270 Delivery Ex-Works
    P14280 Transportation to Sudan
    P14290 Custom Clearance
    P14300 Delivery job site
    P14310 Required on Site (ROS) date
    NFPF.03.04.04 Flexible Hoses (PIP005A)
    P14330 Issue of inquires
    P14340 Issue of purchase order
    P14350 Delivery Ex-Works
    P14360 Transportation to Sudan
    P14370 Custom Clearance
    P14380 Delivery job site
    P14390 Required on Site (ROS) date
    NFPF.03.04.05 Access Fittings (PIP005B)
    P14410 Issue of inquires
    P14420 Issue of purchase order
    P14430 Delivery Ex-Works
    P14440 Transportation to Sudan
    P14450 Custom Clearance
    P14460 Delivery job site
    P14470 Required on Site (ROS) date
    NFPF.03.04.06 Basket Strainer (PIP005C)
    P14490 Issue of inquires
    P14500 Issue of purchase order
    P14510 Delivery Ex-Works
    P14520 Transportation to Sudan
    P14530 Custom Clearance
    P14540 Delivery job site
    P14550 Required on Site (ROS) date
    NFPF.03.04.07 Y Type Strainer (PIP005D)
    P14570 Issue of inquires
    P14580 Issue of purchase order
    P14590 Delivery Ex-Works
    P14600 Transportation to Sudan
    P14610 Custom Clearance
    P14620 Delivery job site
    P14630 Required on Site (ROS) date
    NFPF.03.04.08 Flame Arrestor (PIP005E)
    P14650 Issue of inquires
    P14660 Issue of purchase order
    P14670 Delivery Ex-Works
    P14680 Transportation to Sudan
    P14690 Custom Clearance
    P14700 Delivery job site
    P14710 Required on Site (ROS) date
    NFPF.03.04.09 Expansion Bellow (PIP005F)
    P14730 Issue of inquires
    P14740 Issue of purchase order
    P14750 Delivery Ex-Works
    P14760 Transportation to Sudan
    P14770 Custom Clearance
    P14780 Delivery job site
    P14790 Required on Site (ROS) date
    NFPF.03.04.10 A/G Pipes & Fittings (PIP006)
    P14810 Issue of inquires
    P14820 Issue of purchase order
    P14830 Delivery Ex-Works
    P14840 Transportation to Sudan
    P14850 Custom Clearance
    P14860 Delivery job site
    P14870 Required on Site (ROS) date
    NFPF.03.04.11 Painting (PIP008)
    P14890 Issue of inquires
    P14900 Issue of purchase order
    P14910 Delivery Ex-Works
    P14920 Transportation to Sudan
    P14930 Custom Clearance
    P14940 Delivery job site
    P14950 Required on Site (ROS) date
    NFPF.03.04.12 Fire Fighting Equipment (PIP009)
    P14970 Issue of inquires
    P14980 Issue of purchase order
    P14990 Delivery Ex-Works
    P15000 Transportation to Sudan
    P15010 Custom Clearance
    P15020 Delivery job site
    P15030 Required on Site (ROS) date
    NFPF.03.05 Cathodic Protection
    NFPF.03.05.01 CP Materials under Tank Bottom
    P15050 Issue of inquires
    P15060 Issue of purchase order
    P15070 Delivery Ex-Works
    P15080 Transportation to Sudan
    P15090 Custom Clearance
    P15100 Delivery job site
    P15110 Required on Site (ROS) date
    NFPF.03.05.02 CP Materials for Pilings
    P15130 Issue of inquires
    P15140 Issue of purchase order
    P15150 Delivery Ex-Works
    P15160 Transportation to Sudan
    P15170 Custom Clearance
    P15180 Delivery job site
    P15190 Required on Site (ROS) date
    NFPF.03.05.03 Aluminium Alloy Sacrificial Anode
    P15210 Issue of inquires
    P15220 Issue of purchase order
    P15230 Delivery Ex-Works
    P15240 Transportation to Sudan
    P15250 Custom Clearance
    P15260 Delivery job site
    P15270 Required on Site (ROS) date
    NFPF.03.06 Civil
    NFPF.03.06.01 Piling Material
    P15290 Issue of inquires
    P15300 Issue of purchase order
    P15310 Delivery Ex-Works
    P15320 Transportation to Sudan
    P15330 Custom Clearance
    P15340 Delivery job site
    P15350 Required on Site (ROS) date
    NFPF.03.06.02 Structual Steel
    P15370 Issue of inquires
    P15380 Issue of purchase order
    P15390 Delivery Ex-Works
    P15400 Transportation to Sudan
    P15410 Custom Clearance
    P15420 Delivery job site
    P15430 Required on Site (ROS) date
    NFPF.03.06.03 Fencing Material
    P15450 Issue of inquires
    P15460 Issue of purchase order
    P15470 Delivery Ex-Works
    P15480 Transportation to Sudan
    P15490 Custom Clearance
    P15500 Delivery job site
    P15510 Required on Site (ROS) date
    NFPF.03.06.04 Building Material
    P15530 Issue of inquires
    P15540 Issue of purchase order
    P15550 Delivery Ex-Works
    P15560 Transportation to Sudan
    P15570 Custom Clearance
    P15580 Delivery job site
    P15590 Required on Site (ROS) date
    NFPF.03.06.05 Concrete Material
    P15610 Issue of inquires
    P15620 Issue of purchase order
    P15630 Delivery Ex-Works
    P15640 Transportation to Sudan
    P15650 Custom Clearance
    P15660 Delivery job site
    P15670 Required on Site (ROS) date
    NFPF.03.06.06 Civil Specialty Items
    P15690 Issue of inquires
    P15700 Issue of purchase order
    P15710 Delivery Ex-Works
    P15720 Transportation to Sudan
    P15730 Custom Clearance
    P15740 Delivery job site
    P15750 Required on Site (ROS) date
    NFPF.03.06.07 Culverts Material
    P15770 Issue of inquires
    P15780 Issue of purchase order
    P15790 Delivery Ex-Works
    P15800 Transportation to Sudan
    P15810 Custom Clearance
    P15820 Delivery job site
    P15830 Required on Site (ROS) date
    NFPF.04 CONSTRUCTION
    NFPF.04.01 Site Mobilization
    NFPF.04.01.01 Site Mobilization
    C10010 Civil team mobilize to jobsite
    C10020 Installation team mobilize to jobsite
    NFPF.04.01.02 Construction of Contractor’s Temporary Camp
    C10030 Piling works
    C10040 Water well drilling
    C10050 Steel structure works
    C10060 Building erection
    C10070 Power supply and water supply
    NFPF.04.02 Civil Construction
    NFPF.04.02.01 Site Survey
    C10080 Topographical geotechnical survey
    NFPF.04.02.02 Tank Foundation(Crude Oil Storage TK12001)
    C10090 Excavation
    C10100 Backfilling / compaction (1st-3rd layers)
    C10110 Installation of PVC detection pipes
    C10120 Backfilling / compaction (other layers)
    C10130 Crush gravel ring beam
    C10140 Beding sand (1st layer)
    C10150 Installation of CP grid
    C10160 Bedding sand completed
    NFPF.04.02.03 Tank Foundation (Produced Water Skim TK-12002A)
    C10180 Excavation
    C10190 Backfilling / compaction (1st-3rd layers)
    C10200 Installation of PVC detection pipes
    C10210 Backfilling / compaction (other layers)
    C10220 Crush gravel ring beam
    C10230 Beding sand (1st layer)
    C10240 Installation of CP grid
    C10250 Bedding sand completed
    NFPF.04.02.04 Tank Foundation (Produced Water Skim TK-12002B)
    C10270 Excavation
    C10280 Backfilling / compaction (1st-3rd layers)
    C10290 Installation of PVC detection pipes
    C10300 Backfilling / compaction (other layers)
    C10310 Crush gravel ring beam
    C10320 Beding sand (1st layer)
    C10330 Installation of CP grid
    C10340 Bedding sand completed
    NFPF.04.02.05 Tank Foundation (Diesel Fuel Storage TK-12004)
    C10360 Excavation
    C10370 Backfilling / compaction (1st-3rd layers)
    C10380 Installation of PVC detection pipes
    C10390 Backfilling / compaction (other layers)
    C10400 Crush gravel ring beam
    C10410 Beding sand (1st layer)
    C10420 Installation of CP grid
    C10430 Bedding sand completed
    NFPF.04.02.06 Piling Works
    C10440 Fabrication of piling pipes
    C10450 Piling for pipe racks
    C10460 Piling for building
    C10470 Piling for equipment foundations and others
    C10480 Wedling of pile caps
    NFPF.04.02.07 Fencing and Gates
    C10490 Cast and install concrete base
    C10500 Install poles
    C10510 Install fencing chain and gates
    NFPF.04.02.08 Steel Structure for Pipe Rack
    C10520 Structural steel blasting/priming
    C10530 Structural steel prefabrication
    C10540 Piperack erection
    C10550 Final painting
    NFPF.04.02.09 Other Steel Structure Work
    C10560 Pipe sleeper and supports works
    C10570 Cross-over,platforms,ladders&hand railing
    C10580 Support for cable trays and cable ducts
    C10590 Foundation steel light poles,flood light mast
    NFPF.04.02.11 Control Building Erection
    C10600 Blast & fabrication of foundation structure
    C10610 Erection of foundation structure
    C10620 Erection of support frame
    C10630 Erection of floor / wall / roof
    C10640 Electrical / furnishment / sanitary etc.
    NFPF.04.02.12 33KV Substation Building Erection
    C10650 Blast & fabrication of foundation structure
    C10660 Erection of foundation structure
    C10670 Erection of support frame
    C10680 Erection of floor / wall / roof
    C10690 Electrical / funishment / sanitary etc.
    NFPF.04.02.13 Inst./Mech. Maintanence Shop Erection
    C10700 Blast & fabrication of foundation structure
    C10710 Erection of foundation structure
    C10720 Erection of support frame
    C10730 Erection of floor / wall / roof
    C10740 2.0T SWL overhead crane installation in Workshop
    C10750 Concrete floor for workshop
    C10760 Install equpment, tools and machinery
    C10770 Electrical / furnishment etc.
    NFPF.04.02.14 Other Building and Shed
    C10780 Erection of Guard house
    C10790 D.G set shed
    C10800 Instrument air package shed
    C10810 Chemical injection skid & chemical storage shed
    C10820 Export metering shed
    C10830 Water treatment shed
    NFPF.04.02.15 Road & Grading
    C10840 Construction of 6m wide road
    C10850 Final grading
    C10860 Leveled with crushed stone
    C10870 Concrete work for chemical storage shed
    C10880 Installation of windsock
    C11110 Installation of concrete culvert
    NFPF.04.02.16 Tank Farm
    C11000 Backfilling of earthen bund
    C11220 Construction of internal concrete cover
    C11360 Curb wall between the adjacent tanks
    C11400 Asphaltic surfacing
    NFPF.04.03 Mechanical Equipment Erection
    NFPF.04.03.01 Tank Erection (Crude Storage TK-12001)
    C10890 Tank plates fabrication (cutting)
    C10900 Rolling of tank plates
    C10910 Welding of bottom plates
    C10920 Welding of 1st course
    C10930 Erection of tank roof
    C10940 Welding of other courses
    C10950 Installation of accessories
    C10960 Water settlement test
    C10970 Blasting / painting
    C10980 Insulation
    C10990 Installation of firewater ring & foam
    NFPF.04.03.02 Tank Erection (PW TK-12002A)
    C11010 Prefab./Rolling of internal tank plates
    C11020 Welding / installation of internal tank
    C11030 Prefab./rolling of bottom & shell plates
    C11040 Welding of bottom plates
    C11050 Welding of course plates
    C11060 Prefab./installation of internal assemble
    C11070 Erection of tank roof
    C11080 Erection of lader & accessories
    C11090 Water settlement test
    C11100 Sand blasting and painting
    NFPF.04.03.03 Tank Erection (PW TK-12002B)
    C11120 Prefab./Rolling of internal tank plates
    C11130 Welding / installation of internal tank
    C11140 Prefab./rolling of bottom & shell plates
    C11150 Welding of bottom plates
    C11160 Welding of course plates
    C11170 Prefab./installation of internal assemble
    C11180 Erection of tank roof
    C11190 Erection of lader & accessories
    C11200 Water settlement test
    C11210 Sand blasting and painting
    NFPF.04.03.04 Tank Erection (Diesel TK-12004)
    C11230 Tank plates fabrication (cutting)
    C11240 Rolling of tank plates
    C11250 Welding of bottom plates
    C11260 Welding of 1st course
    C11270 Erection of tank roof
    C11280 Welding of other courses
    C11290 Installation of accessories
    C11300 Water settlement test
    C11310 Blasting / painting
    C11320 Insulation
    NFPF.04.03.05 FWKO (V-12001A/B)
    C11330 Fabricate & install steell base frame
    C11340 Setting,initial align. & associated installtion
    C11350 Final alignment and insulation
    NFPF.04.03.06 Test Separator (V-12003)
    C11370 Fabricate & install steell base frame
    C11380 Setting,intial align. & associated installtion
    C11390 Final alignment and insulation
    NFPF.04.03.07 Heater Treaters (V-12002A/B)
    C11410 Fabricate & install steell base frame
    C11420 Setting,initial align. & associated installtion
    C11430 Final alignment
    NFPF.04.03.08 CPI Separator (X-12001A/B)
    C11450 Fabricate & install steell base frame
    C11460 Setting,initial align. & associated installtion
    C11470 Final alignment and insulation
    NFPF.04.03.09 Gas Boot (V-12013)
    C11490 Fabricate & install steell base frame
    C11500 Setting,initial align. & associated installtion
    C11510 Final alignment
    NFPF.04.03.10 Diesel Fuel Coale.Filters (F-12002A-F,F-12012AB
    C11530 Fabricate & install steell base frame
    C11540 Setting,initial align. & associated installtion
    C11550 Final alignment
    NFPF.04.03.11 Flare Stack(SK-12011)
    C11570 Fabricate & install steell base frame
    C11580 Setting,initial align. & associated installtion
    C11590 Final alignment
    NFPF.04.03.12 Portable Water Treatment Package(SK-12005)
    C11610 Fabricate & install steell base frame
    C11620 Setting,initial align. & associated installtion
    C11630 Final alignment
    NFPF.04.03.13 Flare KO Drum (V-12011)
    C11650 Fabricate & install steell base frame
    C11660 Setting,initial align. & associated installtion
    C11670 Final alignment and insulation
    NFPF.04.03.14 Floating Oil Skimmer(X-12012)
    C11690 Fabricate & install steell base frame
    C11700 Setting,initial align. & associated installtion
    C11710 Final alignment
    NFPF.04.03.15 Fuel Gas Scrubber(V-12012)
    C11730 Fabricate & install steell base frame
    C11740 Setting,initial align. & associated installtion
    C11750 Final alignment
    NFPF.04.03.16 Chemical Injection Skid(Demulsifier SK-12001)
    C11770 Fabricate & install steell base frame
    C11780 Setting,initial align. & associated installtion
    C11790 Final alignment
    NFPF.04.03.17 Chemical Injection Skid (Reverse SK-12003)
    C11810 Fabricate & install steell base frame
    C11820 Setting,initial align. & associated installtion
    C11830 Final alignment
    NFPF.04.03.18 PPD Chemical Injection Skid(SK-12004)
    C11850 Fabricate & install steell base frame
    C11860 Setting,initial align. & associated installtion
    C11870 Final alignment
    NFPF.04.03.20 Closed Drain Sump Skid(X-12003A)
    C11890 Fabricate & install steell base frame
    C11900 Setting,initial align. & associated installtion
    C11910 Final alignment
    NFPF.04.03.21 Open Drain Sump (X-12003B)
    C11930 Fabricate & install steell base frame
    C11940 Setting,initial align. & associated installtion
    C11950 Final alignment
    NFPF.04.03.24 Instrument Air Package(SK-K-12001)
    C11970 Fabricate & install steell base frame
    C11980 Setting,initial align. & associated installtion
    C11990 Final alignment
    NFPF.04.03.25 Nitrogen Generation Package(SK-12010)
    C12010 Fabricate & install steell base frame
    C12020 Setting,initial align. & associated installtion
    C12030 Final alignment
    NFPF.04.03.26 Heat Exchangers(E-12001A/B)
    C12050 Fabricate & install steell base frame
    C12060 Setting,initial align. & associated installtion
    C12070 Final alignment and insulation
    NFPF.04.03.27 Crude Oil Export Pumps(Centrifugal P-12001A/B/C)
    C12090 Fabricate & install steell base frame
    C12100 Setting,initial align. & associated installtion
    C12110 Final alignment
    NFPF.04.03.28 Crude Oil Export Pump(Screw P-12002)
    C12130 Fabricate & install steell base frame
    C12140 Setting,initial align. & associated installtion
    C12150 Final alignment
    NFPF.04.03.29 Emergency Gen./Driver (G-12001/GE-12001)
    C12170 Fabricate & install steell base frame
    C12180 Setting,initial align. & associated installtion
    C12190 Final alignment
    NFPF.04.03.30 Drain Oil Pumps (P-12003A/B/C/D)
    C12210 Fabricate & install steell base frame
    C12220 Setting,initial align. & associated installtion
    C12230 Final alignment
    NFPF.04.03.31 Portable Skimmed Oil Pump(P-12004)
    C12250 Fabricate & install steell base frame
    C12260 Setting,initial align. & associated installtion
    C12270 Final alignment
    NFPF.04.03.32 Portable Water Distribution Pumps(P-12007A/B)
    C12290 Fabricate & install steell base frame
    C12300 Setting,initial align. & associated installtion
    C12310 Final alignment
    NFPF.04.03.33 Diesel Transfer Pumps (P-12009A/B/C)
    C12330 Fabricate & install steell base frame
    C12340 Setting,initial align. & associated installtion
    C12350 Final alignment
    NFPF.04.03.34 Diesel Oil Transfer Pumps (P-12010A/B)
    C12370 Fabricate & install steell base frame
    C12380 Setting,initial align. & associated installtion
    C12390 Final alignment
    NFPF.04.03.35 Flare K.O. Drum Pumps (Centrifugal P-12011A/B)
    C12410 Fabricate & install steell base frame
    C12420 Setting,initial align. & associated installtion
    C12430 Final alignment
    NFPF.04.03.36 Diesel Oil Unloading Pumps(P-12014A/B)
    C12450 Fabricate & install steell base frame
    C12460 Setting,initial align. & associated installtion
    C12470 Final alignment
    NFPF.04.03.37 Metering Skid (SK-12002)
    C12490 Fabricate & install steell base frame
    C12500 Setting,initial align. & associated installtion
    C12510 Final alignment
    NFPF.04.03.38 Water Level Control Box (X-12006A/B)
    C12530 Fabricate & install steell base frame
    C12540 Setting,initial align. & associated installtion
    C12550 Final alignment
    NFPF.04.04 Pipeline / Piping Erection
    NFPF.04.04.01 Underground Piping
    C12560 Trench excavation
    C12570 Welding
    C12580 NDT
    C12590 Flushing
    C12600 Hydrotesting
    C12610 Joint coating
    C12620 Trench backfilling
    NFPF.04.04.02 Aboveground Piping
    C12630 Blast and prime for line pipes
    C12640 Prefabrication
    C12650 Welding / Erection on pipe rack
    C12660 Welding / erection for others
    C12670 Hydrotesting
    C12680 Flushing
    C12690 Final painting
    C12700 Insulation
    NFPF.04.04.03 Water Supply Flowline
    C12710 Excavation of trenching
    C12720 Welding
    C12730 Joint coating and backfilling
    C12740 Hydrotesting and tie-ins
    NFPF.04.05 Electrical Installation
    NFPF.04.05.01 Power and Control Cable
    C12750 Installation of cable tray
    C12760 Cable pulling
    C12770 Meggar test
    C12780 Cable termination
    C12790 Continuity / Meggar test
    NFPF.04.05.02 Electrical Equipment in MCC
    C12800 Install power & motor control centre 400V
    C12810 Install/position 6.6KV switchgear
    C12820 Cabling within package - 6.6kV switchgear
    C12830 Testing - 6.6kV switchgear
    C12840 Install/position DB panel 400v
    C12850 Cabling/termination - DB panels
    C12860 Testing - DB panels
    C12870 Install electrical motors
    C12880 Cabling/termination - electrical motors
    C12890 Testing - electrical motors
    C12900 Install/position A.C. UPS
    C12910 Cabling/termination - AC UPS
    C12920 Testing - AC UPS
    C12930 Install/position D.C. power supply unit
    C12940 Cabling/termination- DC unit
    C12950 Testing - DC unit
    NFPF.04.05.03 Electrical Equipment in Substation
    C12960 Transformers installation
    C12970 Cabling/termination - transformers
    C12980 Testing - transformers
    C12990 Install/position 33kV switchgears
    C13000 Cabling/termination - switchgears
    C13010 Testing - switchgears
    NFPF.04.05.04 Other Electrical Equipment Installation
    C13020 Install diesel generator 400V
    C13030 Cabling/termination - diesel generator
    C13040 Testing - diesel generator
    C13050 Install local control panels
    C13060 Cabling/termination - panels
    C13070 Testing - panels
    NFPF.04.05.05 Lighting
    C13080 Laying the buried cables
    C13090 Installation of lighting poles
    C13100 Outdoor lighting
    C13110 Indoor lightings
    NFPF.04.05.06 Earthing / CP
    C13120 Install copper rod
    C13130 Pull looping cables
    C13140 Grounded to equipment
    C13150 Testing
    NFPF.04.05.07 Electrical Heat Tracing System
    C13160 Install heat tracing elements
    C13170 Install heat tracing panels
    NFPF.04.05.08 Portable Power Station
    C13180 Dismentling and transportation from Diffra
    C13190 Installation in Neem
    C13200 Pre-commissioning and commissioning
    NFPF.04.06 Instrumentation Installation
    NFPF.04.06.01 Cabling
    C13210 Cable tray installation/alignment
    C13220 Cable pulling/laying
    C13230 Cable laying from field instrument to JB
    C13240 Continuity test
    C13250 Cable glanding & termination
    C13260 Look check
    NFPF.04.06.02 Instrumentation in Control Room
    C13270 Install operator interface stations
    C13280 Cabling and termination - operator station
    C13290 Testing - operator station
    C13300 Install Operator push-button station
    C13310 Cabling and termination- push button station
    C13320 Testing - push button station
    C13330 Install building fire alarm panel
    C13340 Cabling/termination- fire alram panel
    C13350 Testing - fire alarm panel
    C13360 Install control system&marshalling cabinets
    C13370 Cabling/termination- control cabinets
    C13380 Testing - control system
    C13390 Install Safety system&mashalling cabinets
    C13400 Cabling/termination-safety cabintes
    C13410 Testing - safety system
    C13420 Install PLC panels
    C13430 Cabling/termination - PLC panels
    C13440 Testing - PLC system
    NFPF.04.06.04 Field Instrumenation
    C13450 Install/wiring of flow meter
    C13460 Install/wiring of transmitters
    C13470 Install/wiring of gauges
    C13480 Install/wiring of ESDV
    C13490 Install/wiring of CV & PCV
    C13500 Install/wiring of PSV & PVRV
    C13510 Install/wiring junction boxes
    C13520 Install air tubing
    NFPF.04.08 Safety Equipment Installation
    C13530 Safety equipment installation
    NFPF.04.09 Tie-ins Into the Exist. Systems & Other Facility
    C13540 Tie-ins with other facilities
    NFPF.05 MECHANICAL
    NFPF.05.01 Pre-Commissioning
    C13550 Pipes & pressurized equip.hydrotest
    C13560 Control of rotating equipment
    C13570 Verification,calibratoin and test of instrument
    C13580 Verification of electrical equipment
    C13590 Verification of electrical circuits
    C13600 Test of safety equipment
    NFPF.05.02 Mechanical Completion
    C13610 Mechanical Completion
    NFPF.06 PROVISIONAL ACCEPTANCE
    NFPF.06.01 Commissioning
    C13620 Commissioning by system
    C13630 Performance testing
    NFPF.06.02 Provisional Acceptance
    C13640 Provisional Acceptance
  4. 0
    Sanjeev Koul ·
    Dear Mr Liu ;

    Thanks for the valuable information.This is eactly what i wanted and it shall surely be very helpful to me to start with.

    Regards

    Sanjeev Koul