Cart before the horse planning
In the Open Standard
Annette HineyMember for 25 years 6 months
- Created
- 0
- 2
0
Guys ’n’ Gals,
trying to work a miracle and get a baseline programme for the construction of a new cement kiln line . The problem is, it is a very congested site and half the equipment is turning up too late to install "properly" and the plant needs to be in production yesterday.
In particular I have a problem with the Raw & Cement mills (gear boxes arriving several months after grinding tables etc.. )Going to have to tackle this as if it were a maintenance task and not a new build. does anyone out there have a programme for an "ATOX" or "OK" mill refit?
Many thanks
Nettie
trying to work a miracle and get a baseline programme for the construction of a new cement kiln line . The problem is, it is a very congested site and half the equipment is turning up too late to install "properly" and the plant needs to be in production yesterday.
In particular I have a problem with the Raw & Cement mills (gear boxes arriving several months after grinding tables etc.. )Going to have to tackle this as if it were a maintenance task and not a new build. does anyone out there have a programme for an "ATOX" or "OK" mill refit?
Many thanks
Nettie
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?