rundown curve

Marcio SampaioMember for 20 years 11 months
Created
3
3
0
Hello all;

Do u know the apllications for rundown curve?

Regards.

3 replies

Oldest first
  1. 0
    Marcio Sampaio ·
    Could u please guide me to find meterials about this topic?

    Best regards.
  2. 0
    Rollen Lopez ·
    Hi Marcio,

    Run-down curves are best applied in items that require follow up to get the value to zero in order to complete the project.
    This looks differently in the normal S-curve as this has an initial value >0 and finally completes on 0.

    One example is that, approval of engineering drawings from the client/consultant which will affect the delay once a timely rundown does not take place.The more higher figure we have for the unapprove drawings, the more we see that our project is concern of delay.

    Same thing applies to the Procurement Packages that has been defined in the original plan. Total Procurement packages should run down to 0 before some construction activity start.

    So our curve will look like a descent hill which our project tracking starts at the top.

    Cheers,

    Rollen
  3. 0
    Marcio Sampaio ·
    Thanks a lot Rollen;

    Could u please guide me to find material or exemples?

    Best regards.