how do you manage and plan the planning process itself?
In the Open Standard
Baiyi LiMember for 19 years 6 months
- Created
- 1
- 7
0
Dear Planners
I foud a very interesting questions. can you please give me some comments
The question is :how do you manage and plan the planning process itself?
the following is Dear Bijaya Bajracharya’s comments;
he stated that The choice is yours. You can have an activity "programme preparation" in your programme. This activity has various steps (P5 terminology) like brain reading drawings and documents, Brain storming meeting with team, outline programme, acceptance of outline programme, draft detailed programme, comments from team, programme review meeting, etc.
It all depends on type of work, size and complexity and risk factors involved.
I foud a very interesting questions. can you please give me some comments
The question is :how do you manage and plan the planning process itself?
the following is Dear Bijaya Bajracharya’s comments;
he stated that The choice is yours. You can have an activity "programme preparation" in your programme. This activity has various steps (P5 terminology) like brain reading drawings and documents, Brain storming meeting with team, outline programme, acceptance of outline programme, draft detailed programme, comments from team, programme review meeting, etc.
It all depends on type of work, size and complexity and risk factors involved.
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?