Slipform Productivity Rates

Ismail VandeliwalaMember for 22 years 5 months
Created
3
2
0
Can anyone please help me with information regarding slipforming productivity rates.

If i am slipforming a lift core how many mts can i achieve per day (this would include the rebar fixing, shuttering for the boxouts/leaveouts, concreting and Slipping the form). Can i continue the slipforming operation without stoppages that is as continous operation?

In the case that it can be done without stoppages how many days would it take to slipform 115m ?

3 replies

Oldest first
  1. 0
    Vishwas Bindiganavale ·
    Ismail,

    Normally in the UAE (for lift cores), it is 3 mts per day. You wouldn’t get an approval from the consultant for anything more than that.

    But, then, slipforms have to be coordinated with crane height - which in turn has to be synchronous with the slabs.

    Ultimately, the corewall casting depends on the slab-to-slab cycle.

    Happy Planning!
  2. 0
    Charleston-Joseph Orbe ·
    Hi Ismail,

    Pick up the phone and ask Sonia of JBR1 or Tara of JBR3 or

    Riswan of DIFC Gate Village or

    You can also check with Arabtec their whereabouts

    Call BRM.

    I agree with Vishwas,

    There is a limitation on how high Core Wall will go up.

    Cheers,

    Charlie
  3. 0
    Karim Mounir ·
    Hi Ismail,

    We used slipform in construction of silos in the project that I’m currently working in.
    Generally, you can operate the slipform 24/7 but you must have enough steel fixers, general labor, concrete finisher, rc concrete, etc..
    You should also consider duration for assembly of the slipform.

    Karim