Considering Baseline schedule
In the Open Standard
Riad BleibelMember for 19 years
- Created
- 3
- 4
0
I am working on a roads/infrastructure project the contractor submitted his preliminary schedule 39 days after getting NTP and the date of the project actual starting date schedule wasn’t in line with the contract requirements. 4 months later after period of ping-pong communication the contractor was able to submit a “Partialy Completed schedule” but kept the activities network untouched as of his early days submittal, in other words he didn’t make any revision to activities start date, duration etc…. during this time many things have been changed for example a CP activity supposed to start 3 months ago didn’t start yet therefore project milstones will be delayed, new site conditions arisen. I had an argument with the contractor that this program can’t be valid with the current project status and after the elapsing of 25% of the contract duration. My question can this schedule be considered as a baseline schedule after this long delay without any revision that is considering the new site conditions ?
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?