Hi to all,


Does anyone know of productivity for scaffolding erection?



thanks,

kier

4 replies

Oldest first
  1. 0
    Tarek Barham ·

    Hi Kier, Have you got any

    Hi Kier,

     

    Have you got any technical figures about scaffolding productivity.

     

    Tarek Barham

    use private message service

  2. 0
    Alain De leon ·

    on formworks

    on formworks (scaffolding,phenolic boards, aluma system)= leadman=0.75/day, skilled=10/day, helper=3/day, units is sq.m

    hope it helps.

  3. 0
    Mike Testro ·

    Hi AlainWhat is the ratio of

    Hi Alain

    What is the ratio of Skilled to Helper and what type of structure is it?

    Best regards

    Mike Testro

  4. 0
    Alain De leon ·

    planned,49 high rise buliding

    planned,49 high rise buliding with a footprint area/floor=2200sqm, ratio helper to skilled is 1:3.33

    formworks works only

Log in or join to reply