productivity rate in Planning Planet (please explain)

Kier LegardMember for 20 years 2 months
Created
0
2
0
hi,


Can someone explain the following productivity rate in planning planet


337 Metal KwikStage, 5 Boards with 2m lifts 11.1 11.9 12.5 m run/hr
338 Metal KwikStage, 5 Boards with 3m lifts 9.1 10.0 10.5 m run/hr
339 Metal KwikStage, House Scaffold with 3 lifts 2.8 3.2 3.8 m run/hr
340 Metal Tube and Fittings, 5-6 Boards wide 3.2 3.7 4.6 m run/hr
341 Tube and Fitting Platforms, 50-250m3 10.6 12.5 18.5 m3/hr
342 Tube and Fitting Platforms, 250-1000m3 18.5 22.5 24.5 m3/hr
343 Tube and Fitting Platforms, over 1000m3 24.5 30.0 33.5 m3/hr
can I use this for reference in steel tube scaffolding erection for bridge falsework?

thanks

kier

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?