scaffolding erection rate in pp
In the Open Standard
Kier LegardMember for 20 years 2 months
- Created
- 0
- 3
0
Hi,
Can someone explain this production rate.Can i use this as reference for scaffolding erection
Ref Task / Description Slow Ave Fast Units
337 Metal KwikStage, 5 Boards with 2m lifts 11.1 11.9 12.5 m run/hr
338 Metal KwikStage, 5 Boards with 3m lifts 9.1 10.0 10.5 m run/hr
339 Metal KwikStage, House Scaffold with 3 lifts 2.8 3.2 3.8 m run/hr
340 Metal Tube and Fittings, 5-6 Boards wide 3.2 3.7 4.6 m run/hr
regards,
kier
Can someone explain this production rate.Can i use this as reference for scaffolding erection
Ref Task / Description Slow Ave Fast Units
337 Metal KwikStage, 5 Boards with 2m lifts 11.1 11.9 12.5 m run/hr
338 Metal KwikStage, 5 Boards with 3m lifts 9.1 10.0 10.5 m run/hr
339 Metal KwikStage, House Scaffold with 3 lifts 2.8 3.2 3.8 m run/hr
340 Metal Tube and Fittings, 5-6 Boards wide 3.2 3.7 4.6 m run/hr
regards,
kier
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?