how can i compare the budget & actual quantity..
In the Open Standard
Jeoffrey ReyesMember for 18 years 3 months
- Created
- 5
- 1
0
hello everybody...
can somebody please help regarding this...our previous planner turned over to me his actual and baseline schedule and seems to have problems on quantity, percent completion, etc...
now, our client give me some comments and i cannot figure out how to correct those errors. one of these problem is like this...
budget Target is 1
actual current is 0
percent completion is 100
difference is 1
how come that it is already 100 pct but actual current is 0.
one more is,
target OD is 12
current OD is 12
currrent RD is 0
percent compltd is 96
i would be grateful if somebody can reply asap. thanks in advance.
can somebody please help regarding this...our previous planner turned over to me his actual and baseline schedule and seems to have problems on quantity, percent completion, etc...
now, our client give me some comments and i cannot figure out how to correct those errors. one of these problem is like this...
budget Target is 1
actual current is 0
percent completion is 100
difference is 1
how come that it is already 100 pct but actual current is 0.
one more is,
target OD is 12
current OD is 12
currrent RD is 0
percent compltd is 96
i would be grateful if somebody can reply asap. thanks in advance.
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?