Tracking a Project With Budgeted Units

Ammar TauqeerMember for 13 years
Created
5
5
0

Hello,

I want to track my project using Budgeted Units on Daily basis. What i want to do is that i want to enter the actual unit daily and want to have a histogram on daily Basis how can i do it. Any Suggesstions or help will be appreciated.

 

Regards

Ammar Tauqeer 

5 replies

Oldest first
  1. 0
    Alain De leon ·

    go to resource usage profile,

    go to resource usage profile, right click resource usage profile worksheet and g profile option, marked actual and budgeted by date and cummulative to get your histogram in a specific resources, change your time scale to week/daily2.

  2. 0
    Ammar Tauqeer ·

    Thanks Another Question is i

    Thanks Another Question is i want to track my project and activity get delayed how would i enter it ? i m chossing Updated Progress option it just updates all the activities in that date i want to delay some activities in that date due to some cirumstances ? How can i do it?

     

    Secondly if my Budgeted units/time are not being achieved daily, i want to make a daily impact of this on my schedule is this Possible?

  3. 0
    Ammar Tauqeer ·

    Thanks Another Question is i

    Thanks Another Question is i want to track my project and activity get delayed how would i enter it ? i m chossing Updated Progress option it just updates all the activities in that date i want to delay some activities in that date due to some cirumstances ? How can i do it?

     

    Secondly if my Budgeted units/time are not being achieved daily, i want to make a daily impact of this on my schedule is this Possible?

  4. 0
    Ammar Tauqeer ·

    Another Question For Example

    Another Question

    For Example in the Status tab, non-labour unit, there is a data field of budgeted Units,Actual Units,Remaining,At complete. My budgeted units are 50 and my activity is for 5 days.Now on day 1 I want to update the status by entering the data in actual units data field that machine works for 10 hours and same on with 2nd,3rd day but on the 4th day it works for 5 hours and also for the 5th day.So it will use another day I want to show that an activity can be delayed by this to 6 days. is this Possible?

  5. 0
    Zoltan Palffy ·

    create a resourceassign the

    create a resource

    assign the resource to each activity

    now you have your planned budget

    now you can update the schedule with actuals weekly

    if the activivity started but not finished put the actual start date and the actual units and the remining units. 

    If the activity started and finished put the actual start date, the actual finish date and the actual units

    if an activity has sarted and is delayed put the actual strta date and actual units and used the suspend and resume option under status