Histograms and S Curves

Sabrina PriceMember for 14 years 8 months
Created
5
2
0

Hi Guys,

I'm new to planning and was wondering if you could help me. How can I extract Manpower Histograms and S Curves from a P6 Schedule.

Thanks

Sabrina

5 replies

Oldest first
  1. 0
    Jose Frade ·

    Hi Sabrina,   Best way is to

    Hi Sabrina,

     

    Best way is to export the manpower to excel (totals by period you need - week, month, etc) and then do them in Excell.

     

    Other option is to use Ressource Usage profile and Spreadsheet  on top icon bar menu.

    Hope it helps

     

    BR

     

    JMFrade

  2. 0
    Rafael Davila ·

    http://www.toolboxforplanning

  3. 0
    Hlamalani Baloyi ·

    Hi Sabrina, I am also new on

    Hi Sabrina,

    I am also new on P6,

    I have just printed my Histogram and S-curve for the 1st time, its easy but you need to know the steps, you can e-mail me: balobros@gmail.com

  4. 0
    Raymund de Laza ·

    Hi Hlamani, Why don't you

    Hi Hlamani,

    Why don't you just post the steps so that others may be shared with your good solution...

    Sabrina is as special as others too...

     

    Thanks,

  5. 0
    Hlamalani Baloyi ·

    Hi Raymund, You are all

    Hi Raymund,

    You are all special to me, trust me.

    I wanted to send her my final spreadsheet so she can check the formulas from there, it will be really difficult for me to explain the formulas on the spreadsheet.

    Otherwise i will send everyone the steps in terms of importing information from P6 and exporting it to Excel,

     

    Thnx guys

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?