Planning blocks of flats/bedrooms (multiple units)
In the Open Standard
Matt WellsMember for 19 years 10 months
- Created
- 1
- 5
0
Does anyone have any experience of planning these types of projects?
At present I am using Asta Powerproject to generate a sequence prorgamme and copying to excel spreadsheets to monitor progress.
This approach is difficult to manage and unscientific as it doesn’t consider trade continuity and is therefore prone to failure.
Does anyone use any dedicated ’line of balance’ software that they can recommend or any other method of planning the finishes of each flat/bedroom? Your help would be most appreciated.
At present I am using Asta Powerproject to generate a sequence prorgamme and copying to excel spreadsheets to monitor progress.
This approach is difficult to manage and unscientific as it doesn’t consider trade continuity and is therefore prone to failure.
Does anyone use any dedicated ’line of balance’ software that they can recommend or any other method of planning the finishes of each flat/bedroom? Your help would be most appreciated.
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?