Skip to content

Auto Rule in P5

Anu TorMember for 19 years 7 months
Created
1
3
0
How can I apply funtion " Link remaining duration and schedule percent complete " in P5

1 reply

Oldest first
  1. 0
    Arnold Puy ·
    Hi Anu,

    This feature is not supported in P5 & P6. However, you can use the % complete type, to do this try the following steps:

    1. Highlight the activity you wanted to apply.
    2. In Activity Details --> General Tab
    3. In % Complete Type, select Physical
    4. Go to Status in Activity Details, change the Physical % & Start/Finish Date
    5. Hit F9 and that’s it.

    HTH

    Arnold

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?