Coal Fired Power Station (With Air Cooled Condensers)

Tom JonesMember for 18 years 6 months
Created
3
2
0
Hi Guys

I have recently joined a power plant project, I previously worked in the mining sector only.

To the guys with power plant experience, can you please supply me with the detail of activities which should make up this schedule.

I am not asking for a complete schedule, or advise on how to plan the project. I only require the detail activities and may be the WBS which they fall under.

email: eljarowalters@yahoo.com

Thanks

3 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear Eljaro,

    What do you want to Construct, the Power Plant or the Air Cooled Condensor?

    Best,

    Samer
  2. 0
    Tom Jones ·
    Hi

    We are constructing the power plant.

    I only made mention of the ACC, to avoid receiving activities with Cooling towers included.
  3. 0
    Samer Zawaydeh ·
    Dear Eljaro,

    The best thing is to review your Contract and check what your company’s scope of work is. Subsequently, you can create the WBS.

    I will send you an email and provide you with what I have.

    Best,

    Samer