CLAIMING AN UNPLANNED HOLIDAY

Bilal TirmiziMember for 17 years 10 months
Created
1
2
0
WE HAD A HOLIDAY IN THE COUNTRY WHICH WAS NOT PLANNED(IT WAS NOT REGULAR HOLIDAY) JUST GOVERNMENT ANNOUNCED THAT IT WILL BE HOLIDAY).

MY QUESTION IS THAT CAN WE CLAIM THIS FROM CLIENT AS WE HAVE BEN CHARDES BY SUBCONTRACTOR FOR MACHINES

IF WE CAN CLAIM HOW WILL I HAVE TO JUSTIFY IT AND IS THERE ANY CLAUSE IN FIDIC FOR THIS TYPE OF CLAIM

1 reply

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear Bilal,
    It depends on your Contract. You will need to know what it allows you and what it does not.
    In case that you have a general Contract under FIDIC and no clauses have been omitted during contract negotiation, then you will need to check clause 8.5: Delays Cause by Authorities.

    It has three clauses that must ALL apply if you want to be submit a claim to be considered:
    1) you are following diligently the authorities.
    2) the authorities delayed or disrupted our work
    3) it was unforeseeable.

    If the above three clauses apply and your Contract is under FIDIC then you can claim.

    Best Regards,

    Samer