48 hours per week Time Period Settings
In the Open Standard
Sam OnumahMember for 18 years 5 months
- Created
- 3
- 4
0
I set the Time Per Period Settings in the User Preference in Primavera (P6.2) to 10 hours a day from Monday to Thursday; and 8 hours on Friday which corresponds to the Workweek settings on the project calendar. when I calculate the schedule the durations give me inaccurate ES/EF dates.
Any suggestions will be appreciated.
Any suggestions will be appreciated.