48 hours per week Time Period Settings

Sam OnumahMember for 18 years 5 months
Created
3
4
0
I set the Time Per Period Settings in the User Preference in Primavera (P6.2) to 10 hours a day from Monday to Thursday; and 8 hours on Friday which corresponds to the Workweek settings on the project calendar. when I calculate the schedule the durations give me inaccurate ES/EF dates.
Any suggestions will be appreciated.

3 replies

Oldest first
  1. 0
    A D ·
    Check ur admin preference settings and also, DEFAULT DURATION FOR NEW ACTIVITIES. (U can find this in general tab in admin preference window)

    Both shud match with ur user preference settings.

    To get a better idea, u may plz contact ANDREW DICK. He has written a beautiful paper on "selection of Calendars and the Admin & User Preferences associated with ‘Units/Time Period’.

    U may ask for a copy from him

    Cheers,
  2. 0
    Sam Onumah ·
    Can you send me ANDREW DICK’s email so I can contact him on his Paper (Selection of Calendars and the Admin & User Preferences associated with ‘Units/Time Period)
  3. 0
    A D ·
    andrewtdick@optusnet.com.au