WBS Sched% compl & Perf % compl inquiry

George RidulmeMember for 18 years 4 months
Created
13
1
0
Hi All,

I have an issue here with my P6. Some WBS level have value on its Perf%compl & Sched% compl (roll up to WBS level) and others does not.

Is my P6 corrupted, or I just missed out something. the activities are resource loaded.


Thanks in advance for your help guys.

george

13 replies

Oldest first
  1. 0
    Mark M ·
    Hi George

    If activities have been added that aren’t included in the baseline this can happen. If this is the case update the baseline with a filter to include the new activties.

    Hope that helps.

    Regards
    Mark
  2. 0
    Arnold Puy ·
    Hi George,

    In addition to what Mark’s info. Try to check also your Price/unit for Resources should not be equal to zero.

    Regards.

  3. 0
    George Ridulme ·

    Thanks guys for your prompt reply.

    I tried and check your suggestion but unfortunately none of it have worked out. I also tried to redo the same program, but the result is still the same.

    am I missing out something here....

    thanks...
  4. 0
    Arnold Puy ·
    Hi George,

    Do you have a baseline in your programme? If yes, then you need to update your Baseline the same with your current. Otherwise, it doesn’t not works.

    Try to check and let us know. As far as I know, this is the reason why it does not show. Performance % complete is related to money.

    HTH.

    Regards.

  5. 0
    Arnold Puy ·
    Hi George,

    Do you have a baseline in your programme? If yes, then you need to update your Baseline the same with your current. Otherwise, it doesn’t not works.

    Try to check and let us know. As far as I know, this is the reason why it does not show. Performance % complete is related to money.

    HTH.

    Regards.

  6. 0
    George Ridulme ·
    Hi Arnold,

    thanks for your help. i tried your suggestion and tried to redo the program several times, but stilll getting the same result.

    I think my primavera is corrupted.

    Thanks & regards,

    George
  7. 0
    Arnold Puy ·
    Hi George,

    If you mind, send me your .xer file and I will try to fix for you.

    Regards.

    Arnold
  8. 0
    Arnold Puy ·
    Hi George,

    Sorry... If you don’t mind, send me your .xer file and I will try to fix for you.

    Regards.

    Arnold
  9. 0
    George Ridulme ·
    Hi arnold,

    thanks for your kindness. can i have your email add. i cant send in your pm ( i think its under mtce now)

    thanks again.
  10. 0
    Arnold Puy ·

    You are welcome.

    My e-mail address is primavera6@live.com

    You can it now since I am still free.. I will just try..

    Thanks.

  11. 0
    Arnold Puy ·
    Hi George,

    I saw the reason why your Performance % & Schedule % complete does not roll-up in your summary is because, when the time you assigned your resources to your activities, you did not mark the checkbox next to "Auto Compute Actuals" & "Calculate cost from units" from Resources workspace --> Details Tab.

    Before you will assign all resources to your activities you must mark the checkbox in order to calculate automatically the budgeted & actual cost during updating.
    Try to notice your current updated activities that some of them is zero for budgeted & actual cost even your price/unit is not equal to zero.

    Try to check and let us know.

    HTH.

    Regards,

    Arnold
  12. 0
    George Ridulme ·
    Hi Arnold & Mark,


    Thanks for your help.

    I really appreciate your kindness. Keep up the good work and please dont be tired helping others.

    Problem solved.


    Regards,

    George
  13. 0
    Arnold Puy ·


    You are welcome George.