What info do yo request to do planning & scheduling?

Johnny SnyderMember for 17 years 3 months
Created
3
3
0
Let’s assume an EPC company has been awarded a major contract to develop a large project. You are hired as Planner and Scheduler to develop the plan and schedule of this large project. On the first days of your new position, what information do you request to do your job? What people do you talk first?

3 replies

Oldest first
  1. 0
    Rubas M. Kutty ·
    Hi Johnny,

    Much of your queries can be found in one of the papers in the Planning Engineers website: http://www.planningengineers.org/publications/papers.aspx

    Look for "Questions to ask when drawing a programme for a construction project" by Gary France. A wonderful read. I hope it’s as applicable to an EPC job too.

    Kind regards

    Rubas
  2. 0
    Samer Zawaydeh ·
    Dear Johnney,

    You can purchase the PMBOK from www.pmi.org and start learning about the Planning Process. It clearly explains the step towards creating a schedule.

    If you have more specific questions afterwards, let us know.

    With kind regards,

    Samer
  3. 0
    R. Catalan ·
    Johnny,

    As a preparation to your programme requirements and in the absence of documents stated in posts 2 & 3, you need to read the following documents, but not limiled to:

    1) Tender Programme submitted during tendering period
    2) Conditions of Contract to check
    a. when to submit the programme
    b. contract/controlled milestones
    c. full/partial access to site
    d. others - need thourough reading
    3) Contract Drawings
    4) Technical Specifications (Scheduling requirements)
    5) Current Progress Status Report (ask for copy of related programmes), if there’s ongoing report
    6) Minutes of meeting
    7) Letter of Award / NTP
    8) Contract deliverables (Bonds, Insurances, etc.)
    9) Ask the Client to have Post-Award Pre-Scheduling Meeting to have a feel or an idea what’s their scheduling requirements
    10) Old datas of similar projects executed by your company
    11) Long-lead items
    12) Production rates and crew compositions
    13).... maybe other PP’ers can add more

    Good luck

    Hope the above helps,

    R*****


Log in or join to reply