Planning A Tower

Arun VasanthMember for 17 years
Created
11
6
0
Hai friends @present Iam working 45 storeyed residential building.I have few quires ...
Area around 4500M2
How much duration we can give for 1 slab for structural & finishing all activities ???
Any body have a template of tower project ???

Working on all departments in one floor will improve the production or not ???

With regards
Arun.V

11 replies

Oldest first
  1. 0
    Anoon Iimos ·
    Arun,

    Before I made this post, I’m the only one who knew that I’m an expert in buildings (now, you know).

    With regards your question, "Working on all departments in one floor will improve the production or not ???"

    My answer is No, but it is necessary as regards inspection and analysis.

    Practically, works cannot be done at the same time, so you need to sequence it, for example: a cycle per floor (including risers). Structural or concreting works shall include rough-ins for MEP - where applicable.

    hope this helps
  2. 0
    Arun Vasanth ·
    Thxs Anoon
  3. 0
    Mike Testro ·
    Hi Arun

    A 45 storey tower is a massive project and if you have never worked on one before I doubt that you have the planning experience to put the programme together without experienced project management input.

    My doctrine which I have stated many times in this arena is "If you can’t build it - you can’t plan it."

    My advice is seek advice on sequencing and logistics from someone who knows how to build it.

    Best regards

    Mike Testro
  4. 0
    Arun Vasanth ·
    Thnxs Mike
  5. 0
    Samer Zawaydeh ·
    Dear Arun,

    The foot print of the tower is small 45 stories x 100 = 4500m2. Or do you have a special shape? In any event, the mentioned area is small for a tower this size.

    You might benefit from the information that I posted in your other inquiry under the same category.

    The best solution is to work with the project team under the supervision of a senior person. And you need to keep asking questions in order to learn what you do not know.

    With kind regards,

    Samer
  6. 0
    Michael Ramos ·
    hi all

    since the topic is planning/building a tower

    maybe we could discuss here the sequences and critical issues/points in building a tower (normal design)

    like:

    corewalls & core slab areas to be ahead from 2 to 10 (in case of slip form and jumpform systems) floors from main slabs to fix the lift inside the building early

    sealing the envelope (curtain wall/cladding) at the soonest to prevent water intrusion (typhoon storms/rains) from flooding the building.

    having the waterproofing of upper floor wet area approved before closing the false ceiling of current floor wet area

    fixing the door shutter before sanitary toilet seats to avoid the laborers abuse of the toilets (in cases where temporary labor waste rooms are limited to every 5 floors)

    fix the door shutter before light fittings and any quick to materials final fix to avoid being stolen

    consideration of material storage ( maybe assigning every 4-5 floors as storage for aluminum materials like glass panels and claddings ).

    appreciate your more inputs thanks

  7. 0
    Arun Vasanth ·
    Thxs A...lot Mycal...
  8. 0
    Rafael Davila ·
    If a concrete structure the following reference might provide you with an introduction on the sequence for shoring and re-shoring.

    http://www.gamcoform.com/dropshore/documents/ACI%20Reshore.pdf

    http://findarticles.com/p/articles/mi_qa5363/is_200602/ai_n21395792/

    As a rule of thumb, we use one level of shoring and two of re-shoring for flat slabs while we use an additional level of re-shoring for concrete joist slabs.

    About the building enclosure this will be interesting, the rest should follow a weekly sequence, maybe 4 stories per week like the Empire State, before the invention of CPM, if using old technology for steel frame buildings.

    from The Empire State Building by Theodore James (1975)

    Official Empire State Building website

    Construction of the Empire State Building began in March of 1930 on the site of the old Waldorf-Astoria Hotel at 350 Fifth Avenue at 34th Street. It was completed 14 months later in May, 1931. Designed by the architectural firm of Shreve, Lamb, & Harmon Associates, the Empire State Building, at 102 stories, was the tallest building in the world until the completion of the first tower of the World Trade Center in Lower Manhattan in 1972.

    For Concrete frames no way to have that speed, it is common for concrete frame buildings to go up at the rate of one story per week.

    Best regards,
    Rafael
  9. 0
    Mike Testro ·
    Hi Arun

    We do not yet know if your tower is steel or concrete?

    If it is concrete then send an email to planning.services@xlninternet.co.uk and I will send you a demo of how to plan a bottom up programme for an insitu structure.

    You are getting bits and pieces of good advice but the main things to consider are:

    1. Shrinking footprint on upper levels - Scaffolding prevents roof cover until struck.
    2. Hook time resource for tower crane.
    3. Weathertight point at each level - see 1. + Cladding.
    4. Max man day resource - cannot exceed provision of site facilities.
    5. M&E commissioning - you will never allow enough time if there is a BMS system.

    Best regards

    Mike Testro
  10. 0
    Santhosh kumar Narayanan ·
    Hi For high rise building take care the following
    1.Sequencing shall start form footing just convering core
    2.Slab will follow
    3. Normally 7 - 10 days per floor if you use slip form
    4. consider duration to install slip form normally 10 days
    5. Provide a link to keep core & slab level difference 3 or max 4 floors to have boom access for concrete.
    6. Consider min 10 day duration for protection plat form around the building prior to start cladding.
    7. You can start cladding upon completion of 15 or 20 floors.
    Use the same cycle of 7-10 days for all finishes per floor assign the resources accordingly.

    8. And many points ofcourse discuss with your PM & CM and other site engineers about the constructability, site access, tower crane location, whinch location (later you need to close that too) etc.

    Reagrds
  11. 0
    Michael Ramos ·
    Inside Works:

    Blockwork starts after removing Scaffoldings on the current floor (usually removed after casting the third slab above the current floor or shuttering work of the fourth slab above)

    Marking and Chasing comes after block then Conduiting works for MEP at wall

    Ducting and Piping supports at Ceiling to follow

    Installation of Ducting and Piping at Ceiling usually comes after plaster