hotel planning

Rola SabbahMember for 16 years 10 months
Created
6
2
0
hi every body
i’m planning a hotel righ now, can somebody send me a time schedule to compare with mine, and have some ideas its a challenging job.
thanx

6 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear Rola,

    Each project is unique, so most probably, having a copy will not assist you.

    Give us a small description of the project that you are working on and we can assist you more.

    With kind regards,

    Samer
  2. 0
    Asd Salim ·
    dear rola
    im ready to help u..just giv me more ideas about ur project
    regards
    salim
  3. 0
    Rola Sabbah ·
    hi
    thank you for your help.
    im planning a hotel of 19 floor , including 3 basements, and a roof that contains a spa and a jim.
    the skeleten is ready, i have to plan the block, EM, Finishes, the external finishes includes, glass, stone,and paints.
    if any body can help me and send me a copy of a hotel plan.
    the problem is the finishes sequence, carpet and finishes, sanitary and risers
    thanx
  4. 0
    Samer Zawaydeh ·
    Dear Rola,

    Let us start after skeleton and you can repeat the activities for each floor:

    I. Rooms
    Block Building
    Door subframes
    Platering Guides
    1st fix EM installation in walls
    Electrical:
    Lighting
    Power
    Low Current
    Mechanical
    HVAC
    Fire Fighting
    Plastering 2nd and 3rd layers
    1st fix under tiles
    2nd fix EM under tiles
    Tiling
    Skirting
    Gypsum Board in Ceiling
    EM Openings in Gypsum Board in Ceilings
    Window Threshold installation
    Aluminum works
    Painting 1st layer
    Painting 2nd layer
    Front Door installation
    Carpeting
    Wood Works substructure
    Wood Works finishings
    3rd fix in wood
    Final Paint
    Curtains
    Paintings
    Loose Furniture
    Commissioning
    II. Rooms Bathroom
    Block Work
    Subframe installation
    Cistern Installation
    Mechanical
    HVAC
    Plumbing
    Plastering Guides
    1st fix EM
    Plastering 2nd layer
    EM works about False Ceiling
    False Ceiling
    Tiling walls
    Floor insulation
    Floor insulation protection
    Tiling Floors
    Door installation
    Sanitary Fixtures installation
    Mirrors installation
    EM 3rd fix in walls
    EM 3rd fix in Ceiling
    Toliet Accessories installation
    Final Paint touch up

    III. Rooms Balcony
    Walls Platering Guides
    Mechanical Drainage
    Electrical 1st fix
    Walls Plastering 2nd and 3d layer
    Tiling
    Parapet threshold installation
    Handrail installation
    Handrail Paint (if any)
    External walls and ceiling paint
    Electrical 3rd fix

    IV. Corridors
    Something similar to the above.
    You can add:
    Service areas at each floor
    Lift Lobby works
    Stair Cases

    Of course all the above is general information, you need to read your BOQ and drawings in order to be more specific. If you need more details, please let us know.

    With kind regards,

    Samer
  5. 0
    Samer Zawaydeh ·
    Dear Rola,

    I also recommend that you have the Roof and the Ground Floor Lobby and other service areas underseparate headings. You can start out by having a list of the rooms at each floor, then you proceed with listing the activities needed for each room.

    With kind regards,

    Samer
  6. 0
    Yasir Arafath ·

    Dear samer,                As

    Dear samer,

                    As i am new to planning field , I am not aware of Building Plan and their activities ,

    So it would be very helpful if you send me  sample copy of  Building plan or hotel project and their activities details.

    My id : yasirlinks@yahoo.com

    Thanks and regards. 

    Yasir arafath 