Planning for Oil & Gas Company

Kumaraganesan KMember for 19 years 6 months
Created
4
1
0
Dear Friends

I need to develop a corporate level plan for an Oil & Gas Development company. The plan should have Level 2 / 3 activities of Seismic Study, Gelogical Modelling & Reservoir simulation, Drilling, etc. It would be helpful if any of you can provide me with a sample plan made in P5 or P6.
Thanks in advance

regards
Kumara ganesan
PP 19077

4 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear K,

    It would be good if you let us know at what stage you are; design, or construction.

    If you let us know the scope of your project, I think that you will have better responses.

    With kind regards,

    Samer
  2. 0
    Kumaraganesan K ·
    Thanks for your kind response Samer. I am now at draft board stage. Scope is that i have to make a corporate plan for Oil & Gas Field Development company. Do you have a sample plan?

    The activites in the company are as below
    1) Approvals from Govt, ministries, authorities,etc
    2) seismic study
    3) Geological Modelling and Reservoir Simulation
    4) Drilling
    5) Prodn Facilties

    I have detail the above activities with WBS frame work.
    Can you help?
  3. 0
    Samer Zawaydeh ·
    Dear K,

    This is very much upper level. You want to have clear categories to start with:

    1. Perlimnary Project Approvals
    1.1 Approvals from Govt, ministries, authorities,etc
    1.2 Site Survey
    1.3 Feasibility Study
    2. Design
    2.1 seismic study
    2.2 Geological Modelling and Reservoir Simulation
    2.3 Operation Design
    2.4 Facilities Design
    3. Financing
    4. Tendering
    4.1 Prepare list of approved Contractors
    4.2 Issue Invitation to Tender letters
    4.3 Contractor prequalifications
    4.4 Tendering
    4.5 Analysis of Tenders
    5. Construction
    5.1 Drilling
    5.2 Prodn Facilties
    5.3 Pipe Racks
    5.4 Storage facilities
    5.5 Administration Facilities
    5.6 Site Security
    5.7 Site Health and Safety
    5.8 Testing and commissioning
    6. Operation
    6.1 Maintenance
    6.2 Administration
    6.3 Security
    6.4 Health and Sagety
    6.5 Delivery
    6.6 Finance
    6.7 Procurement
    6.8 Sales
    6.9 Expansion

    The WBS should encompass all the scope of the project. So you need to discuss it with your team members in addition to the general information that is shown above.

    I hope that some of the information helped.

    With kind regards,

    Samer
  4. 0
    Kumaraganesan K ·
    Samer
    Thank you very much. Thats a great reply from you.
    regards
    Kumara ganesan K