Manhours for piping in trenches

Rinus MijnsbergenMember for 22 years 5 months
Created
2
5
0
Can anybody help me out for which factor(s) to use (based on pipe size in inch)for handling/laying of pre-insulated city heating pipe systems in underground trenches compared to process piping.
Exclusive of excavation, welding and re-filling of trench i.e. only handling, transport on site, set and alignment of pipes.

Thanks in advance, Rinus

2 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Rinus

    Welcome to Planning Planet.

    What exactly is "Process Piping"

    This is a very complex question and you seem to be excluding the main factors that determine productivity.

    Just laying the pipes in the trench is a side issue compared with all the other factors of urban engineering.

    I would be more concerned with traffic control - section lengths - underground obstructions etc.

    Unless of course you are on a greenfield site.

    Best regards

    Mike Testro
  2. 0
    Shazia khan ·
    Hi-Rinus,

    Piping inch dia based on Pipe sch./class , in gerenal we can assume 30- 40 inch Diameter weld per day by one welder, in case of pipeline projects for STD class pipe,

    Pipe trench , execavation depands on soil capacity , we can assume 80 -100 mtr Q. for normal soil.

    Back filling subject to how many equipment you want to use,

    HTH