Eanred Value rules for M&E procurement

Gary WhiteheadMember for 17 years 6 months
Created
3
2
0
Typically a project will earn the value of major M&E kit according to a series of milestones such as order placed, FAT, delivery & installation. The milestones used and % split of value across them is aligned with the T&Cs of the PO.

But I am curious to know what general rules or guidelines do fellow planners follow when developing inital baseline, before the T&Cs are known? And do these guidelines vary across regions and industries?

3 replies

Oldest first
  1. 0
    Shah. HB ·
    Hi Gray

    Are u looking for Earned Value procedure in MEP or WBS in developing the MEP Baseline schedule
  2. 0
    Gary Whitehead ·
    I’m looking for how you apportion the budget cost & assocaited earned value of major M&E kit in your baseline programme

    e.g. perhaps 10% of the value is earned when the order is placed, 50% throughout manufacturing period, 10% at FAT and 30% on delivery
  3. 0
    Shah. HB ·
    Hi Gray

    I have come across a case in which the specification states that delivery of materials Eg,-Generator ,at site cost 75% of Budgeted Value and remaining 25 % goes to the respective installation Activities