Default Curve To All Resources

Shahid ChauhdaryMember for 18 years 4 months
Created
1
4
0

Can we assign / change the default curve on all the resources that are assigned on activities?

Like i want to assign a TRAPEZOIDAL curve to all the resources on all the activities.

1 reply

Oldest first
  1. 0
    Mayukh Datta ·

    resource curve assignment for bulk activities

    Shahid,

    Yes it is possible in P6, but in an indirect way....

    1) You need to define your curve profile first in P6 and give a name.

    2) Export all the activities into excel with "Curve" as a resource assignment field.

    3) Fill the curve profile name in the "curve" profile column in the excel sheet

    4) Import the same file to P6.

     

    This is the indirect way of assigning resource profile to activities in a bulk, else you have to go to the activities one by one and change the resource profile. I understand that any direct method of assigning resource profle to bulk activities in Primavera is still not available.

     

    Hope this answers your query.