Link between specific database and a project planning software

Azar SadMember for 16 years
Created
4
3
0

Hi

I need to know is there any way to link a general specific data base to software such as P3 or P6. our goal is to make this combination an online, decision making tool or self decision maker.

Thanks

4 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Azar I would never allow a

    Hi Azar

    I would never allow a computer to make a decision.

    For instance I never use the resource levelling software.

    Look at the available data and make your own decision.

    Best regards

    Mike Testro

  2. 0
    Vladimir Liberzon ·

    Hi Azar, project management

    Hi Azar,

    project management software is a decision support tool. It supplies decision makers with the analysis of the future consequences of their decisions, answers "what if" questions, and helps to prove that some decisions are better that the others.

    We always use resource leveling because manual leveling in large complex projects produces poor results or is just impossible. So it is reasonable to use computer power to get best results and not just some results.

    But finding optimal resource constrained schedule is hard mathematical problem and most PM software packages (like MSP, P3. P6) produce poor resource leveling results. I think that Mike just never used proper PM software and thus decided to do this very hard job manually.

    I am sure that any PM software supports links to/from external databases. But remember that any scheduling shall be made only if all project acttivities have the same data date. So the process of decision making shall be disreete - at some moment the schedule shall be updated using the data imported from the databases and all actual information. If the schedule is not synchronized - the actual data on different activities and the database data have different dates then no decision shall be made.

    Best Regards,

    Vladimir

     

  3. 0
    Azar Sad ·

    Monte Carlo simulation

    Hi Vladimir

    Do you think using monte carlo simulation tool is useful for strategic decision??? Do you know the scope of this method is how much extended???

    Thanks

  4. 0
    Vladimir Liberzon ·

    Hi Azar, Monte Carlo

    Hi Azar,

    Monte Carlo simulation may be useful for strategic decisions but is rarely used for many reasons that include:

    1) It is time consuming and requires a lot of input data,

    2) Existing Monte Carlo simulation tools are not perfect,

    3) The quality of input information is always low.

    So the results of Monte Carlo simulation using current tools and approaches shall be considered as very rough estimates.

    But estimating necessary contingency reserves and realistic time and cost is necessary and Monte Carlo is one of potential approaches to reciving these estimates.

    We use different approach that is not that time consuming and can be done fast. This approach is a part of Success Driven Project Management methodology. Many publications on SDPM may be found at http://www.spiderproject.ru/publ_e.php#eng

    SDPM is used not only for strategic decisions nut also for regular project management.

    I am sure that strategic decisions shall always be based on risk analysis. So some tools for risk simulation and obtaining realistic estimates shall be used.

    Best Regards,

    Vladimir