Lost hour
- Created
- 6
- 3
Hi can anyone suggest how to monitor works on site by hours? Im using Primavera version 6.7.
Example : inside primavera program we plan to work for 12 hours (7pm to 7am) but actual at site we only can access site in
various hours. sometime we only can work from 8-10 hours per day. Now i need to monitor lost hours on daily
basis. How to show da impact of those 3 or for hours lost time in primavera? If i calculate manually i know how
many days we entittle for. But i dont have any idea on how to monitor ir at primavers? or exc el is da best way
to monitor it?
Hopefully yo get feedback soon
Thank you,
Taz