What is Retained Logic & Override Logic, Some one please explain

Thanx - Tanveer

2 replies

Oldest first
  1. 0
    Tanveer Ahmad Niazi ·

    Thanx Amit cheers

    Thanx Amit

    cheers

  2. 0
    Amit Parmar (PMP) ·

    Hi,I guess its "Retained

    Hi,

    I guess its "Retained Logic" and "Progress Overide" :), the difference between is the way you want Primavera to calculate dates.

    say for example Activity A&b have FS relationship but activity A gets delayed and Activity B starts without Activity A finishing, in this case :

    1) Retained Logic - would follow logic and hence while scheduling Activity B Remaining ES would be calculated from the EF of Activity A, therefore you might see a break in the dates for Activity B.

    2) Progress over ride - This would override logic and schedule both the activities according to the Progress they have achieved. In this case you will not see any break in Activity B.

    Hope it helps,

    Regards

    Amit