Hi all,

I'm new to this forum and I'm looking forward to being a contributing member. I just got assigned to create a project for a small hotel and would your help. Can anyone send me a sample schedule they did so I can compare mine?

If so send to : hijazem@yahoo.com

thank you...

6 replies

Oldest first
  1. 0
    Ulysses Garcia ·

    You are a member since

    You are a member since 2006-09-24

  2. 0
    Ulysses Garcia ·

    You are a member since

    You are a member since 2006-09-24

  3. 0
    Jehad Aldaoud PMP, PMI-SP ·

    You can use the sample

    You can use the sample projects from Primavera program 

     

    best regards 

  4. 0
    Rory Hoban ·

    May have joined pp in 2006

    May have joined pp in 2006 but susa only states "NEW TO THIS FORUM"

    Not sure why you need to highlight this twice

     

    Hi SUSA

    I am also new to this forum - spend most of my time on LinkedIn

    Back to your question - Hotel programme (ask yourself)

    - 1st The sq.m size hotel ie basement construction, number of bedrooms, Kitchen, dining area, bars admin, reception

    - 2nd contract or target programme

    - 3rd How are you going to services this project ie tower / mobile cranes, teleporters, conc pumps / conc tower booms

     

    My hotel Contract programme would look something like:

    - Substructure

    - super structure

    - Roofing

    - Envelope

    - Building seal date

    - Plantroom Structure / lift over run

     

    Internal Finishes

    - Back of house

    - front of house

    - Bedrooms ( would not break out floor by floor for contract)

    - basement finishes

    - lift installation

    - plantroom installation

    - Is FF&E part of your contract

     

    External Works

    - FW & SW drainage

    - watermains

    - site services

    - landscape areas

    - Roads / Paths / Signage

     

    Hope this of use to yourself

  5. 0
    Susa Kamanusa ·

    Thanks Rory for the

    Thanks Rory for the reply,

    Even though I registrered back in 2004 I have never used the forum since then; however, I recently active on the planning scene and plan on being an active member.

    Thanks

  6. 0
    Susa Kamanusa ·

    Dear Ulysses and all, I

    Dear Ulysses and all,

    I registered back in 24-9-2006, but following that in a short time I left the planning field for a while; however, I recently back and active on the planning scene and plan on being an active member.

    Thanks for your inquiry