Skip to content

Man Hour Planning

Kumar BaijuMember for 15 years 8 months
Created
1
2
0

Hi friends

      I want to know the thumb rule for man power planning. For eample:- i am taking 35 hous for detail engineering for equipment design for A1 size, 72 Hous for stress analysis report and so on in my project .similarly i wnat to know the thum rule for construction and erection of steel structure ( manhour per tonne), cable laying ( manhour per metre), Piping erection ( Manhour per inch metre) etc. any refrence or guidence.

 

Regards\\

1 reply

Oldest first
  1. 0
    Maxime AUTHIER ·

    Hi Kumar,   More info are

    Hi Kumar,

     

    More info are required to naswer your question, indeed, steel erection ratio will not be the same for erection of stick-built structure or prefabricated pipe rack; manually cable pulling or with electrical winch, piping erection is also function of location (inside unit or on racks)... ... Maybe you can detailed your request

    In addition, this will also be impacted by the country, either you know the local average productivity factor or you may need to adapt the ratio based on local feedback.

     

    Also, did you look at the rates part of this site, it may contains some.

     

    Rgds,

     

    Maxime.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?