What is the latest ceiling first fix rate (m2/hour)?

2 replies

Oldest first
  1. 0
    Daniel Limson ·

    Nadia, First off, I think you

    Nadia,

    First off, I think you have to mention what discipline or trade are we talking about. If you are talking about installation of ceiling, we also need to know what type of ceiling?

  2. 0
    Mike Testro ·

    Hi Nadia Also a ceiling

    Hi Nadia

    Also a ceiling installation is in at least 3 stages

    1. Main Grid

    2. Sevice tiles

    3. Feild tiles

    each of which has another trade interface.

    4. Commisioning attendance

    There should be a seperate task for each stage.

    Best regards

    Mike Testro