Estimation of Manufacturing Durations for Procurement Activities

Romil VillanuevaMember for 16 years 7 months
Created
3
5
0

Hello good morning to my fellow planners.

I am in a predicament of estimating manufacturing durations which I have to incorporate to my Master Schedule

Most of them are Mechanical Equipments. Strippers, Vessels, Heat Exchangers, Tanks, Filters, In-Line Mixers, Pumps and Compressors. I am hoping that the more senior and experienced planners of our group can help me on this predicament.

Actually I am a new planner for a Petro-chem company so estimating for these equipments are very new to me.

 

Thank you in advance.

 

mil

3 replies

Oldest first
  1. 0
    Sandy Matheson ·

    You need to talk to your

    You need to talk to your procurement people, they should give you these estimates.

    I see now why some people duplicate entries, the 'save' option comes up twice when posting!

  2. 0
    Romil Villanueva ·

    Thanks Sandy, thank you for

    Thanks Sandy, thank you for the reply, I already did but they are also not that confident since we are having multiple vendors....and I was kinda hoping that there is some table which were based on past procurements of similar items and I am yet to hear from them...

  3. 0
    Mike Testro ·

    Hi Romil Send a short

    Hi Romil

    Send a short questionaire email to each of the potential vendors asking for the manufacturing periods.

    Best regards

    Mike Testro

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?