Approval Period Help
In the Open Standard
Rhys ParryMember for 15 years 1 month
- Created
- 7
- 2
0
I have an activity that when it finishes I allow 2 weeks approval until I then start my other activity below this.
How do i go about adding a 2 week approval period as I thought I just needed to add a constriant within my next activity saying start on or after 2 weeks after the end of the first activity in my plan.
My dates are from 20th Febuary 2012 untill 2nd march 2012.
Hope you can help!